Rapid transformation marks new milestone in school construction
Text Tim Janssens, Els Jonckheere, AlheembouwImage Alheembouw

From bottling plant at the former Vandenheuvel brewery to a brand-new educational environment where 860 pupils receive innovative Dutch-language ASO, TSO and BSO education: the creation of the Egied Van Broeckhovenschool is a prestige project through and through. As the first example of the new Flemish DBFM school-building programme, this high-profile redevelopment was also closely watched. The magnificent end result exceeds all expectations, despite a whole host of construction challenges. The considerable attention paid to sustainability, and the application of several circular construction principles, are the icing on the cake.

In 2019, the Flemish Government decided to build on the success of the Scholen van Morgen programme, using the same construction and financing model to deliver 42 new schools, covering a total area of 250,000 m². The first result of this new DBFM programme is the Egied Van Broeckhovenschool, built to a design by B2Ai architects by the ABC 02 consortium, comprising main contractor Alheembouw and financial partner Invesis. Following an intensive two-year new-build and renovation programme, this new campus school, specialising in ‘STEM’ and ‘Society & Wellbeing’, has been fully operational since September 2024. It provides 12,975 m² of classrooms and practical teaching rooms, multifunctional and project spaces, open learning landscapes, a spacious auditorium seating two hundred people, and a semi-underground sports hall with a sports field on its roof. The school presents itself as an open, community-minded project that builds bridges with the neighbourhood. Many of its indoor and outdoor spaces can also be used outside school hours by various associations and the local community.

Exceptionally tight schedule
Transforming the former brewery site into a modern educational environment was no easy task. The planned building programme took shape through an ingenious mix of new-build and renovation work. “The symbolic first stone was laid on 31 August 2022, and one of the school board’s requirements was to have temporary accommodation ready for a hundred first-year pupils just a year later. That is why we decided to fast-track and complete the new-build section,” explains Simon Devos, project manager at Alheembouw. “That certainly didn’t make things easier for us, as the schedule was exceptionally tight, especially since we were also renovating the old brewery at the same time. Among other things, we had to replace the curved roof and demolish a central section to create a patio that would bring in natural light. As a result, we could not start the groundworks for the sports hall until autumn. Nevertheless, we managed to complete the new-build section of the school by the end of June 2023. We also finished the renovation work in summer 2024.”


Versatile mix of materials and techniques
The new-build section of the school comprises two blocks, each with five storeys, including the basement. Almost every material and technique used in traditional construction has been applied. “From a construction perspective, we had to draw on all our expertise to translate the design into reality,” says Simon Devos. “On the one hand, the architect called for unusual brickwork details, a
job that meant bringing in true specialists.
On the other hand, a wide range of finishing materials was specified: facing bricks, plaster, sheet materials, curtain walling, aluminium panels, ceramic tiles and timber terraces. The roofs include both green roofs and conventional waterproofing, including white membranes to improve the performance of the PV panels. Inside, we used, among other things, 15×15-format floor tiles, echoing the flooring in the original buildings, walls with warm timber accents and acoustic spray plaster on the ceilings. This versatile combination of materials and techniques made the project all the more enjoyable and distinctive.”

Renovation brings unwelcome surprises
Major renovation work always brings unforeseen problems. The former brewery was no exception, though there were more issues than had been anticipated. “Once we had stripped the existing building back to its concrete frame, we discovered beams we had not known were there, and found extensive concrete cancer in both the load-bearing structure and the exterior walls. As a result, the plans had to be continually revised, even though the deadline was already very tight. Renovating the exterior façades, with their Art Deco features, took six months in itself,” explains Simon Devos. “Creating the patio, which involved forming a 450 m² opening and then filling it with glass, was also a delicate operation, as ensuring the building’s stability was no easy matter. Reinforcements were needed for the beams, which were quite labour-intensive. Carrying out these structural alterations alongside the other demolition work posed an additional logistical and organisational challenge, when we already had our hands more than full due to the lack of space and the numerous site deliveries.”

Focus on sustainability and ease of maintenance
Even now that the Egied Van Broeckhovenschool has been completed and handed over, ABC 02 remains involved. Under the DBFM contract, BAM FM, as the maintenance partner, is responsible for the building’s structural and technical maintenance for thirty years. “That is why we chose easy-to-maintain systems and materials with a long service life, and placed such strong emphasis on environmental performance. The highly insulated building envelope is complemented by energy-efficient systems such as a KWO system, a CO2-controlled ventilation system with heat recovery, smart lighting, automatic internal solar shading and a 102 kWp PV system. In addition to deciding to reuse as much of the existing building structure as possible, we also applied several other circular construction principles, including reclaimed floor tiles and demountable internal partitions. Alheembouw is keen to focus on DBFM projects, so the Egied Van Broeckhovenschool is a very important reference for us. Combined with the challenging renovation and the specific architectural and environmental requirements, this project is the perfect showcase for what we can deliver in this area.”

Question about this story? Ask your question
Wie aan Egied van Broeckhovenschool werkte
- Technische studies
VK Architects & EngineersMentioned in From bottling plant to open, inclusive school - Inrichtende machtvzw Ignatius Scholen in BewegingMentioned in From bottling plant to open, inclusive school
- ConsortiumBAM PPP PGGM Infrastructure Coöperatie U.A.Mentioned in From bottling plant to open, inclusive school
- architecten- en ingenieursadviesbureau
SwecoMentioned in Egied Van Broeckhovenschool: final construction phase completed successfully - clientvzw Ignatiaanse Scholen in BewegingMentioned in Egied Van Broeckhovenschool: final construction phase completed successfully
- Project managementPREOMentioned in Egied Van Broeckhovenschool: final construction phase completed successfully
- Consortium ABC02InvesisMentioned in Egied Van Broeckhovenschool: final construction phase completed successfully
- interieurarchitectuurB2Ai interior designMentioned in Egied Van Broeckhovenschool: final construction phase completed successfully
- landscape architectureStefaan ThiersMentioned in Egied Van Broeckhovenschool: final construction phase completed successfully
- exploitatie en onderhoudBAM FMMentioned in Egied Van Broeckhovenschool: final construction phase completed successfully