M4 architecten en ingenieurs helps build Maria Middelares’ high-tech logistics platform
Text Geert Van CauwenbergeImage M4 architecten en ingenieurs

At the end of April 2026, Maria Middelares opened its new De Prijkels Logistics and Facilities Platform in Nazareth-De Pinte. M4 architecten en ingenieurs played an important role in transforming an existing building into a future-ready logistics site. Managing director Griet Van den Berghe looks back on an intensive project in which speed, technology and collaboration were central.
For M4 architecten en ingenieurs, working with Maria Middelares was not a leap into the unknown. The architectural practice had already completed projects for the healthcare organisation, including the polyclinic in Gentbrugge, Deinze hospital and refurbishments at Maria Middelares hospital. This established relationship of trust provided a solid foundation for the new project.
“Our team specialises in buildings for the non-profit sector, including hospitals, care homes, schools and nurseries,” says Griet Van den Berghe. “We also deliver residential projects, offices and multi-purpose buildings. For every commission, we approach the landscape, architecture, interior and technical comfort as a whole.”
“At De Prijkels, the challenge was to transform an existing building into a high-performance logistics and facilities platform. Together with the Bruges-based engineering consultancy Ingenium, we carried out extensive work on the existing building and adapted it to its new functions.”

Existing building, new functions
The transformation went far beyond a conventional renovation. “The building was given a new compartment layout. Part of the warehouse was also reconfigured to accommodate automated systems such as the ARS tote system. This required a new, exceptionally flat floor slab with a tolerance of around zero millimetres, allowing up to fourteen totes to be stacked automatically.”
“New annexes were also added for logistics activities, alongside the existing goods loading and unloading bays for lorries. The platform has just three bays, as its large warehouse means relatively few deliveries of medicines and supplies are needed.”
“We also thoroughly reconfigured the interior of the existing building. Part of the original ground-floor office space was converted into production space. The offices were relocated to the first floor and the side building. In addition, the building had to meet specific requirements for the temperature-controlled storage of medicines and related products. An extra plant room was built for this purpose next to the high-voltage cabin, which was also upgraded. The heat pumps and ventilation units are installed outdoors on the ground beside the building, where they are easily accessible for maintenance.”

Space for people and technology
Although logistics and automation were central to the project, M4 architecten also considered the people who work there every day. “Among other things, we redesigned the cafeteria and made the staff facilities more pleasant and welcoming,” says Van den Berghe.
“The high-tech fit-out of the warehouse was an important part of the overall project. Other construction partners, including C&W Logistics, were responsible for fitting out the automated medicines warehouse. Automation and robotics support stock management there.”
The site will play a central role in supplying Maria Middelares’ four clinical sites in Ghent, Deinze, Aalter and Gentbrugge. Bringing the central warehouse and distribution pharmacy together creates an integrated logistics chain that combines efficiency, scalability and patient safety.

Building to a tight deadline
According to Griet Van den Berghe, one of the biggest challenges was undoubtedly the timing. “We did not obtain the necessary building permit for all the external structures until January 2026, even though the opening was already planned for the end of April.
The preparations had already taken a considerable amount of time. As the client, you need to know in advance how you want to work as efficiently as possible in the future. The volume and precise location of the machinery, together with an efficient workflow, first had to be fully determined. It was also important to ensure that the site could be expanded easily in the future without incurring significant additional costs.”
The work was then carried out in several phases. For M4 architecten, this meant not only designing the project but also closely monitoring its progress. “Our role was to work with the client to keep a close eye on the schedule and budget and ensure that contractors and subcontractors stayed on track.”

“The technical aspects also required particular attention. ICT plays a crucial role in a hospital environment and had to be thoroughly tested. The same applied to temperature control and cooling.”
Smooth collaboration
Van den Berghe looks back with great appreciation on the collaboration between all the partners involved. “The right people were around the table, which helped the project move forward smoothly.” She also highlights the client’s commitment, saying they worked around the clock to keep the project on track.
The new platform has also been designed with future growth in mind. “We shaped the project so that the client can continue to grow in the future by adding new machines to the warehouse. In this way, together with our construction partners, we have created a future-ready platform where architecture, technology and healthcare logistics reinforce one another.”
Een zakelijke vraag aan M4 architecten en ingenieurs? Get in touch
Who worked on it
De Prijkels in Nazareth-De Pinte, transformatie
- architect
M4 architecten en ingenieurs - clientMaria Middelares
- Brugse studiebureauIngenium
- inrichting van het geautomatiseerde magazijnC&W Logistics
- construction partnerGLK
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDe Prijkels
- SubjectHealthcare projects
- CompanyM4 architecten en ingenieurs
- CompanyMaria Middelares
- CompanyIngenium
- CompanyC&W Logistics
- CompanyGLK