Circularity on a large scale in a major refurbishment
Text Philippe SelkeImage BPC Group

Brussels’ Northern Quarter has gained another landmark multifunctional office project. The Arch is the result of a large-scale circular refurbishment to the highest sustainability standards. The building, which offers a gross floor area of approximately 14,500 m² across twelve above-ground and two underground storeys, was constructed in the early 1990s, with a low ground floor, limited floor-to-floor heights and numerous reinforced concrete cross-walls. A pragmatic solution was therefore chosen, retaining 70 % of the structural frame while creating as many new openings as possible. The ground floor now features a double-height lobby and an internal street linking the front and rear façades, while open-plan office floors have been created on the upper levels.

Following the much-discussed ZIN project for Befimmo (in collaboration with Van Laere), main contractor BPC Group has once again made a strong impression with this spectacular, sustainable comprehensive refurbishment. The company is thereby affirming its pioneering role in large-scale circular construction. Pierre Danner, Works Director at BPC Group, explains the details of this exemplary project.
Preparation as a construction team
The preparation phase lasted four months, during which BPC Group took a proactive approach to the challenges relating to the building’s structural stability. Pierre Danner: “Having a clear understanding of the structure meant we could respond more effectively to unforeseen circumstances during construction. Overall, collaboration within the construction team was essential to maximising both cost efficiency and the feasibility of measures involving the reuse of materials, such as dismantling the existing natural stone façade cladding.”
In addition to the usual challenges that come with a major refurbishment, with demolition and reconstruction works closely interlinked, construction activities taking place simultaneously, and so on, the project also presented a series of challenges specifically arising from its sustainable and circular nature. The use of geothermal energy, for example, required highly delicate demolition work to carry out the necessary drilling within the building’s own footprint.
Another example: nearly 10,000 m² of lime plaster was applied on the office floors. “This had a major impact on the schedule and organisation,” says Pierre Danner. “Few tradespeople are skilled in this technique, and the work also had to be carried out as late as possible, since the plaster serves as the finish.”


Demolition and reuse
Doors, toilets and urinals, façade cladding, raised access floors … Many existing materials were stored off-site after the building was stripped out, ready to be reused in their entirety or recycled as part of the refurbished building. The lobby, for example, features a terrazzo floor made with recycled aggregates sourced from the original natural stone façades and glazing.
Pierre Danner: “We were fortunate to work for a client that places great importance on sustainability, which is essential to delivering the circular measures envisaged, particularly given the additional costs compared with standard solutions.
This project is undoubtedly one of the most sustainable developments in BPC Group’s history. It is an exemplary demonstration of how a private client’s environmental ambitions can be put into practice coherently and in a financially manageable way.”

A tour de force
Taking into account all the challenges mentioned above, as well as many others not covered in this article, the schedule was extremely tight. The planned construction period was just 24 months. A large project team was therefore mobilised, comprising three site managers and five technicians. “Major refurbishments like this require closer coordination with the consultants, so that unexpected events can be dealt with quickly and work does not grind to a halt. And although we were able to obtain the original as-built drawings, we soon realised that they did not entirely match reality …”, says Pierre Danner.
Despite this, provisional handover at the end of June meant The Arch was completed within the planned timeframe and budget
, a real tour de force for such a complex and large-scale refurbishment project. “In projects like this, coordination between the different parties involved and a good understanding of the challenges are crucial. Thanks to a client who was expressly willing to push boundaries and an architect who took a flexible approach, everything went quite smoothly. I’m proud of what we achieved as a team, and that we delivered exactly within the timescale and budget the client had in mind,” concludes Pierre Danner.
Belcotec, HVAC and electrical services
Having one partner for HVAC and electrical services offers many advantages. This was once again evident in the delivery of The Arch. Belcotec acted as the central point of contact for all building services and electrical systems. “HVAC inevitably involves a substantial amount of electrical work, so a few years ago we decided to add electricity (fire detection, access control, security, lighting …) as a fully fledged additional pillar of our offering. This allows us to deliver ‘combined projects’ such as The Arch successfully. It is therefore an important reference for us, as it demonstrates that we are highly capable of integrating this mix of building services,” says Stijn Geboers, Director of HR, Finance and IT at Belcotec. “As this was a major refurbishment, it was quite challenging. We were already installing new systems while demolition work was still under way on other floors. In addition, a great deal of prefabrication was needed, particularly for HVAC, to save time on site. And of course, large-scale renovations always throw up issues that are difficult to incorporate into a theoretical 3D model. Fortunately, we were able to resolve all the problems smoothly, so overall the project went very well. CORES Development and Studiebureau Van Reeth have since engaged us several times for other projects, so they were clearly happy with our contribution too.”
TECHNICAL DETAILS
Client CORES Development (Antwerp)
Architect B2Ai architects (Brussels, Ghent, Roeselare, Antwerp)
Main contractor(s) BPC Group (Auderghem)