Megadistribution centre for forklift and parts specialist
Text Els GoethalsImage Alheembouw

TVH Group’s expansion seemed unstoppable in recent years. Following the construction of its new headquarters, ‘The Hub’, and warehouse ‘R7’, a 50,000 m² logistics centre is rising on its site in Waregem. We spoke to construction company Alheembouw, which is playing a prominent role in the delivery of ‘Plant T’.
“With Plant T, TVH Group is building its largest distribution centre, featuring an 80-metre-long, two-storey glass walkway connecting its two largest logistics centres,” says Egon Braem, industrial director at Alheembouw. “We are proud that the international market leader has once again placed its trust in us to deliver this state-of-the-art project. Mutual trust is our guiding principle, and it is the starting point for this project too. Rather than opting for a traditional specification, where the price and choice of materials are fixed in full in advance, we chose an open-book collaboration. This ensures transparency and financial openness, allowing us to make informed choices together with the client on materials and phasing. To ensure smooth coordination during delivery within the construction team, everything was coordinated in BIM.”

A carefully designed self-supporting structure
“A project on this scale calls for thorough structural calculations. These led to the choice of two different foundation techniques. A total of 706 displacement piles were installed beneath the fully automated high-bay warehouse, while the logistics centre rests on 1,060 Vibro Concrete Columns (VCCs),” says Tim De Weirdt, project manager at Alheembouw. “The structural design of the self-stabilising high-bay warehouse, with its exceptionally large clear floor area, is also noteworthy. This ensures the smooth operation of the automated racking system and warehouse cranes.”
Plant T in its final phase
“As a BREEAM project, the building places a strong emphasis on sustainable principles and the integration of advanced technologies,” adds Braem. “The first phase of the project was recently completed, and the ground floor has been in use since 1 October. The tight schedule remains on track, with full completion expected in early 2026. Thanks to all our
construction partners.”