With BOEVRIE, property developer Steenoven is adding homes for 135 families to Bruges city centre. For the closed shell, Furnibo combined a large-scale site operation with meticulous technical detailing.
The new residential neighbourhood comprises twelve buildings, each with its own façades, terraces, roof shapes and junctions. Using BIM, 3D scans and meticulous logistical planning, Furnibo made this complex construction project as predictable as possible. The first handovers are now under way.
Twelve buildings at once
“The project looks as though it involves a lot of repetition, but in fact there is almost none,” says Stijn D’hoore, co-CEO of Furnibo. The buildings have a similar technical structure, but differ considerably in form and detailing. Each building volume therefore had to be designed and coordinated separately with the architect and engineering consultancies.
At the same time, the design had to comply with the strict urban planning requirements of Bruges city centre while maintaining the intended architectural quality. The junctions and architectural concrete elements required particular attention. In practice, D’hoore says, the team was building twelve separate buildings at the same time.
The schedule as a living document
For Furnibo site manager Benjamien Fonteyne, the greatest challenge lay in logistics and scheduling. Five tower cranes and an equal number of teams had to be able to work simultaneously. This required precise coordination of material deliveries: a delay to one component could affect the entire construction process.
Some concrete works were therefore carried out at night, in consultation with the city, so that concrete deliveries could take place outside peak traffic hours. The exceptionally wet winter also affected the earthworks and required adjustments. “The schedule is constantly evolving alongside the site,” says Fonteyne. “In practice, things can be quite different from how they look on paper.”
Digital first, then on site
To keep the many junctions and details manageable, Furnibo developed the entire project in BIM. This took more hours than estimated, but the investment proved essential. The team was able to identify problems before prefabricated components went into production or site teams had to work with them.
Client Steenoven also recognised the value of this preparation. According to Steven Langenaken, Head of Construction at Steenoven, Furnibo made a difference even before the collaboration began, by proposing a shallower basement. The developer agreed to this redesign. Using the 3D model, the construction team examined the impact on the drainage network above the car park and developed solutions to drainage issues.
Digital surveying also helped prevent surprises on site at the retained façade on Boeveriestraat. After the former school building was demolished, the façade was scanned in 3D. The point cloud showed that the wall was approximately 30 centimetres thick in some places, compared with the expected 55 centimetres. This enabled the team to adapt the new-build to the existing conditions and develop the junctions together with the structural engineer.
The digital model also provided insight into the later finishing work. Internal walls, door positions and ceiling heights could be assessed at an early stage. This meant buyers’ questions could be addressed before changes on site became costly and disruptive.
Ground-source energy requires careful installation
Beneath BOEVRIE is an extensive BEO field, with 120 boreholes 150 metres deep. According to Langenaken, solar panels could not be used within the heritage context of this project. Steenoven therefore opted for geothermal energy at an early stage. “When we made that decision, this was the first private BEO field of this scale,” says Langenaken. The system heats the homes and also enables passive cooling. This gives residents added comfort on hot days, with limited electricity consumption.
The boreholes had already been drilled before Furnibo began the earthworks. During excavation, some of the pipes became exposed, so work had to proceed with great care. All circuits were tested before the floor slab was laid. Several areas of damage came to light during flushing and could be repaired in good time. “The BEO field is definitely an asset to the overall project,” says Fonteyne. “From an installation perspective, however, it did bring additional points to watch.”
Building together and continuing to adapt
For D’hoore, BOEVRIE confirms the importance of collaboration and clear coordination. On a project of this scale, design, preparation and execution must dovetail closely. On site, experienced staff and young talent worked side by side by design, supported by digital models and specialist departments.
From the façade scan to coordinating five crane teams, predictability came from both preparation and the ability to adapt during construction. In this way, Furnibo helped make room for a new residential neighbourhood within the historic urban fabric. “If you want to enhance city life, projects like this are exactly what you need to do,” concludes D’hoore.