Square One, Geel | Contemporary sustainability on the ring road

At the end of 2019, a brand-new six-storey office complex rose beside Geel’s ring road. Above all, its finely articulated design stands out against the striking setting. Its timeless appearance is a pleasure to behold for passers-by, whether by chance or otherwise.
At the beginning of this year, the entire Netropolix groep team moved to the first floor of Square One. In addition to refurbished workspaces and meeting facilities, the IT company also has extra assembly and storage space. The sixth floor will soon welcome its owner, Tormans. The technical staffing company is seeking tenants for the other four floors, preferably open-minded ‘community workers’. A multi-purpose area beside a central patio on the first floor, with space for relaxation and dining, is shared by the businesses on site and can be used for a range of activities.

At the beginning of this year, the entire Netropolix groep team moved to the first floor of Square One.
Architectural excellence
The track record of Geel-based design practice Archiles architecten speaks for itself. Ir. arch. Jan Van Pelt begins: “Our concept is based on a two-part structure. The ground floor, which houses the entrance hall, bicycle parking, plant rooms and 90 parking spaces, is conceived as a ‘table’ in robust concrete. An office volume with six storeys rests on top. In this ‘light’ structure, maximum daylight and a professional appearance are central. The interplay between crystalline and amorphous materials offers a distinctive and promising perspective. The strict rhythm of the main volume, based on a fixed 130 cm module, ensures a flexible office layout. This is reflected in the façade through the use of vertical aluminium fins. The rather playful effect of ‘open’ versus ‘closed’, depending on whether you view the façade ‘along’ or ‘across’, contrasts subtly with the building’s function as an office.”

In the office volume, maximum daylight and a professional appearance are central.
Technical and environmental performance
And what about sustainability? “Archiles architecten makes no compromises on soundness and quality,” says Van Pelt. “Every component of the project must contribute to a sustainable end result. To maintain control as designers, we developed the entire project in 3D using Revit. This model enabled us to respond quickly and refine the design where necessary, verify its overall technical coherence in light of the required flexibility, and draw inspiration when tackling complex studies, such as detailing the glass façade. Working to strict quality standards is an integral part of our calling card. The same applies to aspects such as energy efficiency and ecology. For this project, for example, we opted for a geothermal heat pump system to achieve optimum temperature control using a renewable energy source. A spacious outdoor patio and roof garden on the first floor act as the building’s ‘lungs’. The ground level is also being landscaped. After a refreshing walk beside the large pond, which also provides rainwater attenuation, employees can get back to work feeling reinvigorated!”

For an office environment, the quality of the finishes is particularly high.
Flawless finishing
In September 2019, Olens construction and interior design company Beneens won the VOKA-Kamer van Koophandel Mechelen-Kempen Enterprise Award. There was little time to savour the achievement: work at Square One began in early October 2019, focusing on the entrance area and sixth floor. Project manager Sanne Verschooten, who is steering the project together
with colleague Hans Ver Elst, explains: “Beneens is responsible for floor screeds and finishes, painting, and the installation of Gyproc partitions and furniture on every floor. The first floor, occupied by the Netropolix groep, was completed at the end of 2019. The deadline for the other floors is early March 2020. We are finishing the Tormans floor entirely to measure, in close consultation with the client. Floors 2 to 5 will have a basic finish with flexible layout options. On completion, future tenants will already have a kitchenette, a climate ceiling and sanitary facilities.”
Teamwork is the glue
“The tight deadline,” replies Verschooten when asked about the biggest challenge. “In our business, we depend on other parties involved. Before Beneens can start, the building must be complete and in optimum condition, for example, watertight and windproof. For an office environment, the quality of the finishes is particularly high. Careful preparation, planning and overall ‘lean management’ nevertheless enable us to meet our objectives. Multidisciplinary teamwork, fruitful collaboration and efficient communication, behind the scenes and on site with our fantastic skilled tradespeople, are unquestionably the cornerstone of the results we can already see today.”
Question about this story? Ask your question
Who worked on it
Square One in Laakdal
- architectArchiles architecten
- vloeropvullingen en -afwerkingBeneens