General

A brand-new swimming pool for Blankenberge

Text Josefien De BockImage Skyvision

Het 25 meterbad is het enige zwembad met zeewater in ons land.
Het 25 meterbad is het enige zwembad met zeewater in ons land.

Construction of a new sports complex for the municipality of Blankenberge began in August 2021. Two and a half years later, ‘De Sportdoze’ was complete. The project includes a swimming pool and a sports hall and mat room for basketball, bowling and martial arts. The modern site also features a skatepark.

Since its establishment in 1979, A C H Bouw has built a strong reputation in the Belgian construction sector. The company works on residential, commercial and industrial projects. As part of the S&R Group, the construction specialist has completed many notable projects. “Through S&R, we introduced techniques and processes that were well ahead of their time,” says Office Manager Patrick Van Gestel. “We have been part of the construction team for more than twenty years, and have rolled out this successful formula on other projects too.”

Innovative techniques and processes

This also applies to A C H Bouw’s many public-private partnerships and the DBFMO principle. This means the construction company works closely with the architects, engineering firms and clients to develop projects progressively, from the drawing board through to handover. “We always take every aspect of construction into account, from client requirements, efficiency and affordability to building maintenance. We bring this wealth of experience and expertise to all our projects. Public tenders continue to dominate our sector, of course. Yet we find that our reputation and expertise set us apart, and that clients are always satisfied when we win a contract,” says Patrick Van Gestel.

A range of building materials were brought together in a single structure.

A brand-new sports complex in Blankenberge

In 2021, the Noordzeebad in Blankenberge, which dates from 1974, was due for renewal. “Renovation was not an option, so a new building was needed. Following a public tender, client FARYS/TMVW awarded the project to A C H Bouw,” says project manager Gerrit-Jan van der Veen. ‘De Sportdoze’ comprises a sports complex with two large sports halls for all official sports, such as basketball and volleyball, and for competitive matches. There is also a hall for martial arts clubs, a dance studio and a multi-purpose room. The new Van Audenaerde swimming pool features an eight-lane competition pool (seawater), a five-lane teaching pool (fresh water), a slide, two toddler pools with play features (fresh water) and an eight-person whirlpool. A retractable stand with seating for two hundred people is also provided.

“We spent the first year working mainly below ground, and the second above ground. The biggest challenge on this project was bringing together so many different construction methods and materials in one structure. We worked on three construction streams at the same time: the sports hall, the central zone and the swimming pool, which made the project complex. The swimming pool, for example, has a timber roof with glulam beams and Swiss roof panels, while the sports hall is built on a steel structure with hollow-core vaults. This required our construction team to draw on very different expertise. Our many years of experience in building swimming pools and sports halls were undoubtedly a major asset,” says Gerrit-Jan van der Veen.

‘De Sportdoze’ comprises a swimming pool, sports complex and skatepark.

Belgium’s only saltwater pool

The 25-metre pool, which has a 20.5 by 7.5-metre movable floor with a 3.3-metre hinged section, is filled with seawater. It is an ideal swimming environment for swimming clubs and recreational swimmers. “The swimming pool in Blankenberge is unique, as it is the only saltwater pool still in operation in Belgium. A seawater pool requires all materials to withstand salt, including tiles, pumps and water treatment systems. As saltwater pools have not been built in Belgium for a long time, we had few precedents to draw on for this project. Thanks to our strong construction team, which at one point numbered around eighty people on site, and close supervision on site, we brought the project to a successful conclusion,” explains Gerrit-Jan van de Veen.

After two and a half years of construction, ‘De Sportdoze’ was complete. The sports halls, swimming pool, cafeteria, reception desk and sports department offices are now all housed in one building. The project cost a total of 20 million euros. In return for this investment, Blankenberge has gained a new social hub. “The staff can also work more efficiently, as everything is centralised in one location. The complex was built using the most sustainable technologies, including a green roof and solar panels. This means lower energy consumption than the old, poorly insulated pool. In many ways, this new swimming pool represents a major step forward for Blankenberge,” concludes Gerrit-Jan van der Veen.   

TECHNICAL DETAILS
Client FARYS (Ghent)
Architect ESSA (Diest)
Main contractor(s) A C H Bouw (Antwerp)

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow