West Flanders

BRUSK brings together technology, sustainability and timeless architecture

Text Guy De MeulenaereImage Musea Brugge

BRUSK brings together technology, sustainability and timeless architecture

BRUSK, the new art hall of Musea Brugge, opens its doors in mid-2026. It is a place where art, architecture and sustainability blend seamlessly. The design strikes a rare balance between monumental ambition and urban refinement.

“The building does not reveal itself straight away,” say the architects. “Just like Bruges itself, which you only really get to know through its narrow streets and hidden places.” The architecture invites exploration. Via the Scala Grande, a monumental staircase with views of the Belfry, you move from urban Bruges to the green tranquillity of the museum park. “There is a sense of anticipation in the space,” says architect Paul Robbrecht. “The building seems to be waiting for what is about to happen: an exhibition, a meeting, an idea.”

Visitors enter a bright public zone with a café, bookshop, auditorium and educational spaces. “The ticketed programme was deliberately placed on the upper floor,” says architect Olivier Salens, “so that the ground floor could become an open, welcoming, transparent and completely freely accessible space that people can walk through, as it were, and which is in a sense given back to the city.” The decision was also made to make the museum’s educational role visible. The youth workshops and auditorium are clearly visible as visitors and passers-by stroll through the building. “It is a place where people who do not visit museums also feel at home,” says Olivier Salens.

Light as a building material

The first floor houses two monumental exhibition halls measuring 40 x 40 and 20 x 40 metres. Their height, of up to 13.5 metres, subtly evokes churches and cathedrals. The natural light has been masterfully calibrated. Each hall has a north-facing window that slopes upwards, as in Monet’s studio. 

The diffuse light entering the building makes the space itself a setting that constantly adapts to the exhibition. Paul Robbrecht hints at light as a fully fledged building material: “It determines the atmosphere, orientation and even rhythm. The building breathes serenity. It is a quiet dialogue between art and construction.” 

The art hall forms part of a new 2-hectare arts site. (Image: Olivier Salens)
Light determines the atmosphere, orientation and even rhythm.
The building breathes serenity.

Sustainability in every fibre

What really sets BRUSK apart is the way sustainability is an integral part of the design. The roofs are clad in photovoltaic glass scales that supply the building with renewable energy without detracting from views of the historic city. The glass scales are an aesthetically pleasing and technically sound solution.

Beneath the building is a BEO field that provides natural heating in winter and cooling in summer. BRUSK will share the system with the neighbouring Groeningemuseum. This makes the art hall more than twice as energy-efficient as the current BEN standard. The principles of circular construction were also applied to the fullest extent, with a focus on reusable materials, low-maintenance systems and a long service life.

An oasis between stone and greenery

The art hall forms part of a new 2-hectare arts site featuring research centre BRON, the renovated Groeningemuseum and a museum park. Mature trees have been retained and woven into a new green setting where visitors can literally find room to breathe. Even a small canal, currently overgrown, is to be brought back to life. 

BRUSK is a model of sustainable architecture, as well as an invitation to pause and wonder. A building that anticipates, embraces and breathes.    

PROJECT DETAILS

Client City of Bruges

Architects Robbrecht en Daem architecten (Ghent) and Olivier Salens Architecten (Bruges)

Main contractor(s) Blaton (Brussels)

Precision on point for a prestigious project

Behind BRUSK’s expressive architecture and technical complexity lies painstaking surveying work that leaves no room for error. For this, main contractor CIT Blaton called on the expertise of Landmeetkunde & Expertiseburo Teugels in Temse, a family business with fifty years’ experience in topographical precision.

Words by Guy De Meulenaere | Image: Teugels

The greatest challenge lay in constructing the roof.

“We were not involved right from the first phase,” says Steven Buytaert, surveyor and director at Landmeetkunde & Expertiseburo Teugels. “We came to the site when the structural works began to assist the contractor. This started with setting out the foundations, basement walls and concrete walls. At a later stage, we were asked to take height measurements, establish levels and check the anchor points for the steel structure.”

High precision

The greatest challenge lay in constructing the BRUSK roof. It comprises a series of slopes and complex junctions supporting photovoltaic glass scales. “We had to set out the fixing points with the utmost precision so that the roof structure could be built perfectly,” Steven Buytaert continues. “That may seem simple on paper, but in practice it demands a high degree of accuracy. This is where our experience really came in handy. A difference of one millimetre at the start can lead to major
deviations by the end of the project.”

The close collaboration between surveyor and contractor also proved crucial here. “On projects of this kind, you can only achieve a good result if all the parties trust one another implicitly. The contractor did an excellent job, which meant the whole process ran very smoothly.”

As a sworn surveying firm, Teugels combines half a century of relevant experience with advanced technologies, including 3D laser scanning and drone surveying. The company now has more than thirty employees and fourteen surveying teams working in Belgium and abroad. Each project is carried out by a surveyor working alongside a survey assistant. This not only speeds up the measurements, but also provides an additional check.

Landmeetkunde & Expertiseburo Teugels joined the project during the structural works phase.

A special project

“For us, accurate is only just good enough,” concludes Steven Buytaert. “BRUSK was a special project for us, first and foremost because of the technical demands, but above all because of the location itself. In a city with the history of Bruges, among centuries-old buildings, a contemporary habitat is taking shape that fits perfectly into its surroundings. That is what is so rewarding about our work: seeing a building grow from the precise lines and points you have set out yourself.”    

Question about this story? Ask your question

Who worked on BRUSK

  1. ClientStad BruggeMentioned in A state-of-the-art museum takes shape in the heart of Bruges: BRUSK
  2. ArchitectRobbrecht en Daem architectenMentioned in A state-of-the-art museum takes shape in the heart of Bruges: BRUSK
  3. Main contractorCIT BlatonMentioned in A state-of-the-art museum takes shape in the heart of Bruges: BRUSK
  4. goods liftStove LiftenMentioned in A state-of-the-art museum takes shape in the heart of Bruges: BRUSK
  5. architectsOlivier Salens Architecten (Brugge)In this story
  6. Main contractor(s)Blaton (Brussel)In this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBRUSK
  • SubjectWest Flanders
  • CompanyOlivier Salens Architecten (Brugge)
  • CompanyBlaton (Brussel)