High-tech storage facility on the banks of the IJzer
Text Iris SalembierImage Alheembouw, Ringpartners-Gent Architecten en DENEIRE

We are at Heernisse industrial estate in Diksmuide. A stone’s throw from the iconic IJzertoren, a new high-tech tower rose here last year: the fully automated high-bay warehouse of Avasco Industries. We spoke to two key members of the construction team who worked together to deliver the project.
Avasco Industries’ high-bay warehouse is essentially a giant storage rack that serves as the load-bearing structure and is clad with wall and roof panels. Measuring 2,900 m² (66 x 44 metres) and standing 36 metres high, the warehouse can accommodate no fewer than 21,808 pallets across sixteen levels. The fully automated warehouse is equipped with an Automated Storage & Retrieval System (ASRS), which automatically places each pallet in the correct location. These fully unmanned warehouses are considered the future for local businesses. As well as being cost-effective and efficient, they are also highly sustainable. They are built almost entirely from recyclable materials such as steel and rock wool panels, which provide insulation and temperature control without additional energy consumption.

An elegant giant
Stijn Laleman of Ringpartners-Gent Architecten has worked with Avasco Industries for more than twenty years and tells us about the specific challenge posed by this type of structure: “This is not really a building, but a machine. So the design started with a giant block.” The architect nevertheless ensured that this behemoth remained visually appealing. “We opted for horizontal bands in a colour gradient from dark grey at the bottom to white at the top. This makes the volume appear less massive while allowing it to sit discreetly in its surroundings.”
The fact that the industrial estate is in a flood-prone area also presented its own challenges. The loss of flood storage capacity was only just avoided. “Given the nature of this type of warehouse, there was little we could change to meet the requirements,” says Stijn Laleman. “In my view, this is not something that can be solved plot by plot. The issue needs to be addressed across the entire industrial estate.” As a precaution, the warehouse stands on a 1-metre-high concrete plinth, with the lowest row of pallets also 1 metre above ground. This also provides capacity to contain firefighting water, as required by the fire brigade.

No space to waste
Another key construction partner was Alheembouw. “Avasco Industries contacted us and the architect together,” says Egon Braem, Industrial Director at Alheembouw. “This meant that we, as contractor, were closely involved in the entire project from an early stage. At Alheembouw, we find this kind of project much more interesting than fully developed projects where we are simply there to carry out the work. This way, we were able to help make the construction as economical as possible.”
One of the biggest challenges was the limited space on site. “Avasco’s baseline, ‘No space to waste’, applied during construction too.
The warehouse uses the plot right up to within 5 metres of the boundary. This called for tight logistics planning and precision during the works.” Alheembouw was responsible for the structural work, finishing and coordination of the various partners. Close collaboration with the architect, engineers and overseas specialists ensured that construction proceeded without any significant problems and that the warehouse was completed in less than a year.

DENEIRE: Earthworks and landscaping
DENEIRE played a crucial role in the construction of Avasco Industries’ high-bay warehouse in Diksmuide. The family business carried out the preparatory earthworks and landscaping, including liming the subsoil and installing the foundation for the piling rig, an essential step in constructing the impressive racking structure. After construction, DENEIRE built a fire access road around the warehouse using permeable paving blocks. A retention basin was also installed beside the existing buildings, with a permeable car park built over it. These sustainable solutions were necessary because the industrial estate lies within the IJzer floodplain. “For us, earthworks involve more than simply moving earth,” says Leen Deneire. “It is about providing a solid foundation, both literally and figuratively. Our years of experience ensure that every project is carried out with precision.” DENEIRE is known not only for its technical expertise, but also for its focus on trust and collaboration. “We have worked well with Avasco Industries for many years. They are, after all, our neighbours at the site in Kleine Dries,” continues Leen Deneire. “We also carried out all the earthworks and landscaping in Vlamertinge at the time.” Collaboration with the other construction partners involved, including main contractor Alheembouw, also went smoothly. This ensured the project was carried out efficiently.
PROJECT DETAILS
Client Avasco Industries (Diksmuide)
Architect Ringpartners-Gent Architecten (Ghent)
Main contractor(s) Alheembouw (Oostnieuwkerke)
Question about this story? Ask your question
Who worked on it
Hoogbouwmagazijn Avasco Industries in Diksmuide
- clientAvasco Industries
- architectRingpartners-Gent Architecten
- main contractorAlheembouw
- grondwerken en omgevingsaanlegDENEIRE
Keep following this
Get an email when a new story is published. No account needed.
- ProjectHoogbouwmagazijn Avasco Industries
- SubjectWest Flanders
- CompanyAvasco Industries
- CompanyRingpartners-Gent Architecten
- CompanyAlheembouw
- CompanyDENEIRE