A well-designed foundation concept for a new school campus

Work is nearing completion on a new Dutch-language school campus in the centre of Schaarbeek, for 1,140 pupils.
The site lies between Gallaitstraat and Vanderlindenstraat, covers an area of 21,700 m² and spans a difference in level of 4 to 5 metres. Even before construction work began, this called for extensive foundation works, which brought significant logistical and organisational challenges.
Words Tim Janssens | Images Lameire Future Foundation Technics
The Brussels-Capital Region has been grappling with a severe shortage of school places for many years. An ambitious, multifunctional DBF project such as Campus Gallait is therefore a welcome addition. Between Gallaitstraat and Vanderlindenstraat in Schaarbeek, a new nursery, primary and lower secondary school has been built, along with shared facilities including a sports hall, a dining hall, an arts and creative space, a workshop and a laboratory, as well as an underground car park with 53 spaces. A little further away, an existing heritage depot has been converted into an upper secondary school, with a dining hall, shared support facilities and a youth centre. Campus Gallait is conceived as a ‘village in the city’, bringing together several schools across two clusters on a single site, where pupils of all ages can interact and the wider community and local residents are also welcome. The youth centre, intended for the youth organisations Chiro Schaarbeek, Ratatouille and Transfocollect, completes this broad educational concept.

There is a difference in level of 4 to 5 metres between Gallaitstraat and the Vanderlindenstraat behind it.
A range of foundation techniques
Before the new school buildings could be constructed, Lameire Future Foundation Technics, part of the 2Fund group, laid the foundations for this
forward-looking project, both literally and figuratively. Project engineer Nicolas De Pestel explains: “To create the underground levels, we first installed a retaining wall on both clusters to retain the soil and groundwater, using secant piles. The pile wall is 450 metres long and consists of around a thousand secant piles, 15 to 19 metres deep. The depth varies depending on the location on site, as there is a difference in level of 4 to 5 metres between Gallaitstraat and Vanderlindenstraat behind it, sloping down towards Vanderlindenstraat, so we worked in steps. The pile wall ensures stability, retaining the ground over heights ranging from 4 to 9 metres, and also serves in part as a foundation for
the new buildings. Around 300 ground anchors ensure horizontal stability. Finally,
460 soil displacement screw piles were also drilled from excavation level.”

The secant pile wall is 450 metres long and consists of around a thousand secant piles, 15 to 19 metres deep.
A logistical jigsaw puzzle
The Gallait site is in the heart of Schaarbeek, inevitably bringing with it several logistical constraints. “Everything had to be brought in through a fairly narrow entrance on Vanderlindenstraat, at the back of the site, as the busy tram traffic on Gallaitstraat could not be disrupted under any circumstances,” explains Nicolas De Pestel. “In addition, other work was taking place at the same time as the foundation piles were being drilled, including earthworks and dewatering, so we also had to take account of the other contractors on site. Combined with the scale of the project, this presented a considerable challenge. Even so, everything went very smoothly, thanks to the excellent cooperation with the main contractor and the fact that the techniques used are part of our everyday work. The level differences on site and the relatively large retaining walls, up to 9 metres high, are certainly no insurmountable obstacle for an experienced contractor such as Lameire, so we can rightly call this a successful project!”
TECHNICAL DETAILS
Client Vlaamse Gemeenschapscommissie (Brussel)
Architect POLO Architects (Antwerpen, Brussel)
Main contractor(s) BESIX: Vanhout (Geel)
Foundation works Lameire Future Foundation Technics (Eeklo)
Een zakelijke vraag aan Lameire Funderingstechnieken? Get in touch
Who worked on it
Campus Gallait in Schaarbeek
- foundation works
Lameire - clientVlaamse Gemeenschapscommissie
- architectPOLO Architects
- main contractorBESIX
- main contractorVanhout
Keep following this
Get an email when a new story is published. No account needed.
- ProjectCampus Gallait
- SubjectEducation
- CompanyLameire Funderingstechnieken
- CompanyVlaamse Gemeenschapscommissie
- CompanyPOLO Architects
- CompanyBESIX
- CompanyVanhout