Seven floating classrooms for a school in Schoten

Pupils at Burgemeester Marnixschool in Schoten moved into their new school building, the Piano, after the half-term break. Its seven floating classrooms are supported by a column structure.
The new school wing was wind- and watertight by the start of the 2020 school year. Final handover followed in December.


Burgemeester Marnixschool dates back to the 1980s and consisted of a single-storey school building. As pupil numbers grew rapidly, the primary school gradually outgrew its premises. But adding an extra floor on top of the building was not an option. The original building’s foundations were inadequate. So a33 architecten designed an impressive column-supported structure for the school, providing 625 m² of floor space and seven new classrooms. The new extension floats above the ground floor. The main challenge for the builders at PIT Antwerpen? Carrying out the work during the school year.

Work continues through the summer holidays
Thanks to the work, pupils at Burgemeester Marnixschool started their summer holidays two days early last year. PIT Antwerpen began the school extension on 29 June 2020. Project manager Jens Verheyen: “The existing building had an atrium with a dome. We removed it so that we could build our column structure. The downside was that the school’s atrium flooded when it rained. We designed a special structure to turn it into a watertight basin. We worked as quickly as possible, including during the construction holiday, to have the shell ready by 1 September and limit the risk of water ingress. Our machines and cranes were off the playground before the first day of school.”

All the other work followed in the autumn, including the installation of plumbing and electrical services and the fitting of plasterboard walls. Separate entrances for the workers and pupils meant that normal school life could continue. PIT Antwerpen had completed the work by the Christmas holidays. “I coordinate work at a lot of schools. Timing is always important there, because pupils must be disrupted as little as possible,” explains Jens Verheyen. “The trick is to coordinate the schedules of all the subcontractors very carefully. I always try to work with regular teams. The workers know how to work well together. That helped us finish on schedule.”
Precisely drawn up
Didn’t Covid cause too many problems? “We weren’t affected by it. Our steelwork contractor had drawn everything up in detail beforehand, allowing other parties to integrate their building services and external joinery into the plans. All the other workers used the same plans as a basis, so everything could be finalised in advance. The plans were ready and all the materials had been ordered before April 2020. If the project hadn’t been drawn up so precisely, those deadlines would have been difficult to meet.”
The pupils have now moved to the new floor, with its high-ceilinged classrooms and varnished OSB floor behind a sleek white façade. Jens Verheyen: “The client was very satisfied and surprised that we had managed to complete the work in just six months. That’s what it’s all about for us!”
“The new school building was completed in just six months, thanks to thorough preparation”
Een zakelijke vraag aan PIT Antwerpen NV? Get in touch
Who worked on it
Piano in Schoten
- architecta33 architecten
Keep following this
Get an email when a new story is published. No account needed.
- ProjectPiano
- SubjectEducation
- Companya33 architecten
- CompanyPIT Antwerpen NV