A green crown for healthcare in Ghent
Text José MulderImage Stijn Bollaert

The Ghent skyline has changed for good. Alongside the familiar centuries-old Boekentoren, designed by Belgian architect and artist Henry van de Velde, the university campus now boasts a second landmark tower: Nobel I. Named after Nobel Prize winner Corneel Heymans, this futuristic building is more than just an architectural feat. It is a functional building that supports the completion of UZ Gent’s masterplan, which aims to create an innovative, sustainable and flexible hospital.

The brief was clear: the architect and contractor had to take care of the design and permits themselves, then deliver a building at speed that met all the requirements and the programme of requirements. The consortium of MBG, LOW architecten and Wiegerinck hit the mark on every count, capping their work with a literal crown. Project lead Geert De Waele explains: “The design was effectively pushed underground, with the excavated soil replaced on the roof. This gave the building a beautiful green crown, helping to fulfil the ambition of creating a healing environment.”

From masterplan to masterpiece
Although the tower’s final function was not yet entirely clear, the intention was to build Nobel I as quickly as possible. During the first phase of Project U, the building would serve as temporary accommodation for several departments, including outpatient clinics. It went from a blank sheet to completion in a very short time, using the Design & Build model. Running several processes in parallel made it possible to deliver results at exceptional speed. The building was designed above all with the wellbeing of its users in mind.
Thanks to its considerable height and full-height windows, the building enjoys excellent natural light. Geert De Waele says: “The entire façade is made of glass. This makes the interior feel spacious and gives you a sense of being connected to your surroundings, not least because of the wonderful views. The stairs and lifts are grouped centrally. This means every space around the core has a window and therefore plenty of natural light. Passive solar shading is used to control solar gain and heat.” This takes the form of an overhang. When the sun is high and the heat intense, it is kept out.
In winter, when the sun is low, it shines inside to create a pleasant sense of warmth. The overhang is also made up of solar panels. So the sun is not only kept out, but harnessed to generate green electricity for heating and cooling the building. This means the heat pumps can be used effectively throughout the year, operate more efficiently and help maintain a more stable indoor climate.

Smart, flexible design
To make the spaces future-proof, they had to be built for flexibility. All services, including drainage, are therefore routed through raised floors. If a space is given a different function in the future, it can be renovated and adapted without causing too much disruption to the spaces next door, above or below. Geert De Waele explains: “We are also using Nobel I as a test site. It allows us to trial things on a relatively small scale and see whether they will work on a larger scale too.”
One example, alongside the heat pumps and PV solar shading, is the switch from DECT to Voice over Wifi, so that internal communications run through a single system. Innovative choices were also made in terms of safety. Instead of conventional compartmentation, an advanced sprinkler system was installed, as is often the case in American hospitals. The system tackles fires at source, reduces the risk of extreme heat and prevents the danger of explosions. This is a major advantage in a building with sensitive functions such as laboratories and cleanrooms. To prevent legionella, only instantaneous water heaters are used.

A symbol of people-centred innovation
“Nobel I is a test bed for smart systems, entirely in keeping with the tower’s purpose: research. If they prove successful, they will later be used in the new central hospital building. All these choices have been made with human wellbeing as the starting point,” says Geert De Waele. “Now that the building is in use, we can see what works well and where adjustments may be needed or possible. One of the first things we noticed was how the large windows perform. To maintain a comfortable feel, we need to increase heat output slightly on darker days. If it looks cold, it feels cold. On warm days, of course, the opposite applies, so we adjust that too. The message is clear: everything is geared towards making the user experience as comfortable as possible.”
Once the new central hospital building is complete, Nobel I will be converted to its original purpose: a fully fledged research centre with cleanrooms and high-tech laboratories. By then, a learning landscape will have taken shape, with healthcare at the heart of the campus. Patients and students will each follow their own route, another decision intended to improve human comfort. The ambition is clear: UZ Gent aims to become a living lab for healthcare and science. Nobel I brings everything together, from innovative construction technology to people-centred care, and from scientific research to sustainability. The building is a beacon of progress, showing how the hospitals of the future are already taking shape today.
Cegelec: Building services
Cegelec, a VINCI Energies brand, played a crucial role in delivering the full building services package for the Nobel I project. It was responsible for all building services: plumbing, control systems, electrical installations and sustainable systems. Project Manager Christophe Van den Bossche says: “Because we have all the technical disciplines in-house, we can take a multidisciplinary approach and keep communication channels short.” The tight construction schedule required Cegelec to take an active part in lean planning. This integrated approach reduced frustration on site and increased client satisfaction. Alongside integrating the different technologies into the Building Management System (BMS), the company delivered sustainable solutions. For example, the lighting uses absence detection: users switch the lights on using a push-button, and they switch off automatically when no one is detected. Cegelec also installed the other systems: high- and low-voltage switchboards, UPS, data cabling, ASTRID, access control, fire detection, heat pumps, ventilation, split units, central heating and cooling, BMS, softened water, mains water, greywater recovery and fire mains. The impact of Cegelec’s work is evident in the finished building and offers valuable lessons for the future. “Our coordinated building services demonstrate the added value we bring. This is a major advantage for contractors, both during design and on site.”
PROJECT DETAILS
Client UZ Gent (Ghent)
Architect LOW architecten (Antwerp) and Wiegerinck (Arnhem, the Netherlands)
Main contractor(s) MBG (Antwerp)
Question about this story? Ask your question
Who worked on it
Nobel I in Gent
- ClientUZ Gent
- ArchitectLOW architecten
- ArchitectWiegerinck
- Main contractorMBG
- technical installationCegelec
Keep following this
Get an email when a new story is published. No account needed.
- ProjectNobel I
- SubjectHealthcare projects
- CompanyUZ Gent
- CompanyLOW architecten
- CompanyWiegerinck
- CompanyMBG
- CompanyCegelec