Seniors move into the 21st century with respect for heritage

At the beginning of 2019, all residents of Sint-Elisabeth care home, run by Zorgbedrijf Rivierenland, will move into a brand-new building in Sint-Katelijne-Waver. The care home will also get a new name on this occasion: Bosbeekhof.

The building materials have been combined in a varied yet harmonious way: red variegated brick, wood-effect cladding, architectural concrete and fibre-cement cladding.

“The new building is the first of three phases in an overall project,” explains Sander Theunis, project engineer at main contractor Antwerpse Bouwwerken. “Once the residents have moved in, we will start the next phase, namely demolishing part of the existing care home. In the section that is retained, we will make a number of structural alterations, creating a ‘merger’ with the new building at ground-floor level. This section will house a local service centre with a cafeteria, a beauty salon, a fitness room, a multi-purpose hall and classrooms, followed later by the offices of Zorgbedrijf Rivierenland. Given the practical difficulties involved, this renovation phase will require the most attention. Phase 3 consists solely of demolishing the existing kitchen and the former administrative centre of the local OCMW.”

BIM
Antwerpse Bouwwerken is using BIM (Building Information Modelling) on this project. “This enabled us not only to avoid potential construction clashes, but also to use large prefabricated wall panels, columns, beams and staircases, speeding up the construction process.” The main contractor also took a proactive role in optimising the design. “Originally, a load-bearing structure of steel trusses and a tie rod was planned,” says Theunis. “At our suggestion, this structure was modified, with only the sloping trusses retained. }

Antwerpse Bouwwerken worked not only with subcontractors, but also with other contractors on the project. “As this collaboration is a dynamic process throughout the construction period, clear agreements are essential to bring the project to a successful conclusion,” says Sander Theunis.

We placed them on a concrete support so that their weight is transferred to a concrete beam. Working with the engineering consultancy, we achieved a compliant load transfer without compromising stability.”

Monastery
The old care home was part of a monastery complex. “The existing monastery proved unsuitable for conversion into a new care home that meets current standards,” explains Kristof Gebruers of CONIX RDBM Architects. “Converting it into serviced apartments was not feasible, either structurally or financially. In addition, the monastery building is on the heritage buildings list, so its valuable sections had to be preserved.”

Living groups
The new building has three storeys. It contains 92 rooms, the same number as the old building. Bosbeekhof is divided into living groups of seven or eight residents. Two living groups form one unit and share a communal bathroom and storage rooms. Each floor has a servery kitchen, from which meals are served buffet-style. The unit for residents requiring enhanced supervision is on the ground floor, with direct access to an enclosed sensory garden.  

Question about this story? Ask your question

Who worked on it

Bosbeekhof in Sint-Katelijne-Waver, nieuwbouw

  1. main contractorAntwerpse Bouwwerken

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBosbeekhof
  • SubjectHealthcare projects
  • CompanyAntwerpse Bouwwerken
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.