Klein Veldekens, Geel | Complex engineering for electrical installations

Klein Veldekens, Geel | Complex engineering for electrical installations

Starting with the electrical services (high-voltage substation, UPS systems, emergency power supplies, diesel generator, etc.) and finishing with access control, the data network, fire detection, lighting and more: this was the task facing Elektriciteitswerken Janssens on the Astor project. “Our initial scope was very loosely defined, but in the end we took responsibility for the complete engineering of virtually all the electrical installations. Fortunately, we were able to handle the associated challenges smoothly, thanks to our extensive experience in healthcare construction,” says managing director Peter Ledoux.

Elektriciteitswerken Janssens can rightly describe the construction of the Astor buildings in Geel as a ‘turnkey project’. With the exception of the nurse call system, which the client installed itself, the company installed all the electrical systems on site. “It wasn’t an easy project because a number of changes were made ‘en cours de route’, with the aim of optimising everything down to the last detail,” explains Peter Ledoux. “This meant that the project involved a huge amount of engineering and drafting. It was also our first time working with CLT. At first, it took a bit of getting used to, especially as the construction process was very fast, with one floor every two weeks, and we had to integrate all the cabling into the floor build-up at tremendous speed each time. But in the end, it all worked out well. Looking back, perhaps we could have got even more out of it, for example by drilling the light points into the prefabricated timber frame structure in advance. That is certainly a lesson we will take into future projects.”

No rocket science

Elektriciteitswerken Janssens is familiar with building care homes. The Astor site was therefore not its first project of this kind. “Our extensive experience in healthcare construction was a major advantage on this project,” says Ledoux. “Although the complex incorporates every conceivable electrical system, it was certainly no rocket science from a technical point of view, and the work went smoothly. The main challenge was that we had to add to the installation every week, submit new plans, modify sections and so on. It was also a real luxury that
we could draw on our many years of knowledge and expertise, and working with main contractor Hooyberghs was as enjoyable as ever. We are currently working on the final details. By the end, we will have spent around 16 months working on the Astor site. It was an extremely intensive and complex project, particularly given the sheer volume of preparatory work, but the result is well worth it!”     

Question about this story? Ask your question

Who worked on it

Astor in Laakdal

  1. elektrotechniekenElektriciteitswerken Janssens
  2. main contractorHooyberghs

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAstor
  • SubjectHealthcare projects
  • CompanyElektriciteitswerken Janssens
  • CompanyHooyberghs
Share this article

Advertisement

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.