Multifunctional extension sets the tone for a new healing environment
Text and images Tim Janssens

Ziekenhuis Oost-Limburg plans to modernise and expand its Genk campus extensively over the coming years. To manage this large-scale renewal programme, it drew up an ambitious master plan to be implemented in three phases, with 2032 as the target completion date. The first sign of this transformation is the R building, which houses rehabilitation facilities, a GP out-of-hours service and the Sexual Assault Care Centre, among other services. With its flexible structure and attractive appearance, this light-filled, welcoming building symbolises the changes the hospital site will undergo in the coming years.
Ziekenhuis Oost-Limburg (ZOL) was established in 1995 following the merger of Sint-Jansziekenhuis in Genk, André Dumontziekenhuis in Waterschei and Sint-Barbaraziekenhuis in Lanaken. The healthcare campus in Schiepse Bos is the result of an initial master plan drawn up in 1996, based on an existing hospital building dating from 1983. As healthcare needs have changed significantly since then, the hospital site required an infrastructure upgrade. To prepare ZOL for the future and create space for specialist care activities, a new master plan was developed, focused on creating a healing environment.

Around 50,000 m² of development space is planned in total, without significantly increasing the hospital’s footprint. Comfort, wellbeing, sustainability and greening are the guiding principles behind the ambitious expansion plans, which will be carried out in three phases. The first phase, running until 2025, is dedicated to the construction of the R building and the extension of block K, which will house the cardiology centre, the new cardiology day clinic and the radiotherapy bunker. A new car park tower will then be built, and the existing car park will be transformed into a green park. In addition, new buildings for critical care services (the emergency department, operating theatres and intensive care) and 16 nursing units, including a mother and child centre and psychiatric services, will be delivered between 2025 and 2030. Finally, the third and final phase will add a 14,000 m² nursing block and a 6,000 m² consultation complex, including the new entrance, registration area and a healthcare boulevard with specialist retail outlets.
Rehabilitation in a woodland setting
The first project on the agenda was the construction of block R, a flexible, multifunctional building of 5,400 m² with a basement, ground floor and four upper floors. All rehabilitation facilities on the campus have been brought together in this light-filled, welcoming building, which also accommodates the Prometheus GP out-of-hours service, the Sexual Assault Care Centre, overnight accommodation for doctors, business and office space, and consultation rooms. Four basic materials, concrete, wood, aluminium and glass, combine to create a sense of calm and harmony, as well as a strong connection with the woodland surroundings, supporting the recovery process and mental wellbeing of patients undergoing rehabilitation. In other words, the R building is a crucial first step towards a healing environment.
The striking design is by LOW architecten and Wiegerinck. “Our practices complement each other very well and often work together as equal partners. Given our excellent working relationship and efficiency, the project’s short lead time was no obstacle,” says Ruud Boeckx, senior tender manager at LOW architecten.
From the outset, the client knew that the schedule of requirements could still change significantly, even after the building came into use. This led to the choice of a flexible layout with several shell-and-core zones, partially embedded in the sloping site to preserve its natural contours. As a result, the main entrance is integrated into the transparent public plinth on level -1. An additional entrance on the ground floor serves the cardiac rehabilitation department, while the first floor houses multidisciplinary outpatient clinics, connected to the adjacent G building by a footbridge.

Natural materials
The R building is transparent in every sense of the word. It benefits from abundant natural light, and its clear structure, equally clear layout and carefully planned circulation routes make it easy for healthcare professionals and patients to find their way around. “We used natural materials wherever possible to move away from the sterile look and feel that characterises many hospital environments,” explains Ruud Boeckx. “The building’s structure consists of a concrete frame, partly prefabricated and partly cast in situ. It is surrounded by an external façade of prefabricated timber-frame modules, clad in light-coloured anodised aluminium façade panels. The panels reflect their surroundings, helping the building blend into the landscape. Large windows offer wonderful views of the green surroundings, which are actively used as part of the rehabilitation process, including through the creation of dedicated trails. This creates a seamless transition between indoors and outdoors, symbolising the path towards independence.”
“One of the main construction challenges was building the timber mezzanine in the double-height rehabilitation space of the sports medicine centre on level 3, which effectively forms a floating floor,” says Annemie Symons, project manager at main contractor MBG. “The CLT structure is suspended from substantial steel sections using large tension rods. Each element weighed 1.5 tonnes and had to be brought in along the side of the façade, which was no easy task. Building the steel footbridge to block G was also challenging. This 30-metre-long structure is made up of four large trusses. It required extensive preparatory surveying, and installation was also quite complex. Working in a hospital setting also meant meeting specific logistical requirements. The entrance and exit for ambulances were located on the street side and had to remain accessible at all times. Combined with the tight turning space and limited storage area on site, this required meticulous coordination.”

Fast, efficient delivery
For this project, MBG formed a temporary consortium with VMA, which was responsible for the HVAC and electrical installations. “We are both part of the multidisciplinary CFE Group, which creates an interesting synergy. Wherever possible, we therefore try to offer our services together,” says Filip Guisson, Project Manager BU Buildings at VMA. “The electrical installation includes three main switchboards for normal power, emergency power and UPS. The technical systems cover a wide range of healthcare requirements: DALI-controlled lighting, nurse call systems, fire detection, data network, CCTV, access control … The heating system combines an ATES system with a heat pump. Technically, the project was not a mammoth undertaking, but one unusual aspect was that several zones had to be released early so they could be brought into use. While the rest of the building was still being completed, those zones already had to meet fire safety requirements and pass inspection. That was no easy feat.”
Work began on 30 August 2021, and practical completion took place on 20 February 2023. The building has been in use since 27 February. “We tailored the construction concept to the tight schedule and short delivery period,” emphasises Annemie Symons. “For example, most of the timber-frame façade, including the aluminium external joinery, was manufactured in the workshop. This meant that installation on site could be carried out very quickly and efficiently. We were able to install eight timber-frame elements a day, so it took just a week and a half to complete an entire façade. We could then move straight on to the internal finishes, which had already started very early. The plasterboard walls were even installed before the façades were in place, allowing VMA to start work on the technical systems. This was not always straightforward, but it paid off in terms of timing. The fact that the project was fully developed in BIM, at LOD 400, which is a high level of detail, certainly helped, as did the excellent collaboration with the architects. All this resulted in smooth delivery and an impressive end result!”
Question about this story? Ask your question
Who worked on it
- ClientZiekenhuis Oost-Limburg (Genk)
- ArchitectLOW architecten (Antwerpen) en Wiegerinck (Arnhem, Nederland)
- Main contractor(s)TM MBG (Antwerpen): VMA (Sint-Martens-Latem)