Renovating the Royerssluis requires the site to be drained

Text and images G. Smeyers

Als expert in bronbemaling is G. Smeyers verantwoordelijk voor de grondwaterstanden op de werf.
Als expert in bronbemaling is G. Smeyers verantwoordelijk voor de grondwaterstanden op de werf.

The Royerssluis in the Port of Antwerp was officially opened in 1907. Since 2021, the century-old lock has been out of service for a major renovation and deepening project. It is a feat of engineering that has brought several experienced contractors together under the banner of the Rinkoniên Consortium. As the team’s preferred groundwater expert, G. Smeyers was appointed to keep the dewatering works at the Royerssluis on track.

A network of sensors monitors the complex construction site.

The Royerssluis initially served as a sea lock and later primarily served inland shipping. Renovating and deepening an existing lock requires meticulous control of the water. An aerial view shows the lock squeezed between the Scheldt and the docks, with work on the Oosterweelknoop nearby. A thorough preliminary study was essential, and G. Smeyers carried it out at its own engineering consultancy. Its modelling and calculations determine the pace and safety of the entire project. Drawing on its extensive expertise in the various dewatering techniques, the company is responsible for groundwater levels on site and for the geothermal systems in the future buildings there.

Innovation on and off site

Before the earthworks could get under way, the groundwater had to be lowered sufficiently within the cofferdams that had been installed. To achieve this, G. Smeyers used its own ‘digbag method’, saving valuable time. Dewatering throughout the lock was then accelerated using around 80 combi wells within a water-retaining wall extending down into the clay. 

The Royerssluis is a complex construction site, which G. Smeyers continues to monitor using a network of sensors. The client can also track water levels and other parameters on and around the site via a custom-developed cloud application. This virtual representation is a major asset that G. Smeyers also deploys on other sites. Once the groundwater has been lowered sufficiently, the earthworks will begin this summer. The renovated Royerssluis is scheduled for completion by the end of 2026.     

Een zakelijke vraag aan G. Smeyers N.V? Get in touch

Who worked on it

Royerssluis in Antwerpen, renovation

  1. grondwaterexpertG. Smeyers

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRoyerssluis
  • SubjectRenovation
  • CompanyG. Smeyers N.V
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.