A sleek new look for a social housing block calls for precision work
Text Tim Janssens en Niels RouvroisImage Renotec

After sixty years exposed to the elements, the social housing units in the Essegem district of Jette have seen better days. An energy retrofit was therefore needed, with a complete renewal of the façade as one of its main priorities. The facelift of block 4, which is now well under way, sets the tone for the further upgrading of the site, both in terms of thermal and energy performance and visual appeal.
The Essegem district has a total of six social housing buildings, constructed between the 1970s and 1990s. They are grouped around a green public space with seating and a small playground, among other features. The apartment block currently being refurbished by Renotec (block 4) contains 66 homes, managed by social housing association Lojega.

An attractive linear pattern
Uninsulated walls, mould growth, thermal bridges ... these are just some of the problems that needed to be addressed. Renotec is restoring the building to a healthy condition through a major energy retrofit, including literally and figuratively giving it a new look. “The apartment block is getting a special metal skin, with profiled sections that we have to align perfectly with one another,” explains project manager Jorne Gielen. “By combining perforated and non-perforated cladding, we create the effect of an attractive linear pattern without changing colour. A flat façade would have been easier, but we enjoy a challenge. The windows have also been replaced, as have the reveals, both inside and out, and the balconies. The latter, which previously measured 60 cm by 3.5 metres, have been cut back and replaced with a robust steel structure measuring 1.60 by 6 metres. This gives residents much more room to get some fresh air outdoors. We are not only improving their comfort, but also adding value to the building as a whole, which will soon have a much more attractive appearance. It is rewarding to turn an ageing concrete structure into an attractive, modern apartment block that meets all today’s requirements.”

Bespoke work through and through
Although block 4’s new façade will look particularly sleek, there is a great deal of complexity behind it. “Alignment is the main challenge. Because of the unusual shape of the profiled façade cladding, no two window junctions are the same. Every window therefore has to be finished to measure, which is unusual on projects of this kind. And since there are no vertical joints and only one or two horizontal joints per floor, we have little room for manoeuvre and have to work with great precision. Everything has to be right to achieve a neat, seamless finish. As a result, some details had to be redrawn to make them feasible in practice, which involved a great deal of work. It also took some careful planning to conceal the steel columns, beams, rainwater downpipes and so on behind the metal façade cladding. The fact that residents are continuing to live in their flats while we work, making safety, communication and coordination especially important, does not make things any easier. In short, there have been and continue to be various challenges and complexities, but it has been a valuable learning experience. We have made good progress, and our working relationship with the architecture firm Canevas (part of Bureau Greisch) and the client is excellent. If the weather holds, we will be finished in spring 2024.”
Question about this story? Ask your question
Who worked on it
Sociaal woonblok Lojega Jette in Jette
- energetische renovatieRenotec
- architectural practiceCanevas