Case study: Cordeel’s new headquarters

Case study: Cordeel’s new headquarters

Cordeel’s new headquarters is much more than a calling card. The building also showcases the company’s expertise and economic ambitions. It goes without saying that this called for the highest possible quality in every detail of the construction. Discover this exceptional project below…

Cordeel chose to establish its new headquarters on the site of the former ‘De Boelwerf’ shipyard in Temse. The company has brought together its services for the Belgian market on a 20-hectare site. The new building was constructed directly above an old dry dock. It takes the form of a bridge, supported on both banks of the dry dock, which, at 560 metres long and 55 metres wide, is the largest in the world. It could accommodate the construction of two large ships at a time. “After the shipyard went bankrupt, operations at the dry dock ceased. But by building our headquarters 20 metres above water level, we are keeping all options open for the dock to be repurposed or reused in the future,” says project manager Gert Hoefnagels.

Two enormous trusses

Visitors to Cordeel’s site are immediately struck by the building. The long horizontal ‘beam’, with a clear span of 72 metres, extends beyond the two support columns on either side with cantilevered beams measuring 17.40 m to the north and 19.40 m to the south. Its total length is therefore more than 100 metres, and it is 26 metres wide. The ‘beam’ is 14 metres above ground level and 20 metres above water level. It comprises two enormous trusses, each 10 metres high. The trusses were assembled on site by Aertssen, a subsidiary of Cordeel Groep. They were connected in three parallel planes by crossbeams spaced 3.60 m apart, designed to support the building’s floor slabs and flat roof. The entire frame was then positioned on the support columns using two heavy-duty cranes, with great precision.

The steel frame weighs 1,200 tonnes in total. It goes without saying that moving this volume of steel and placing it on the support columns on either side of the dry dock called for top-level expertise and meticulous planning. Four hollow reinforced-concrete columns, each measuring 100 x 60 cm in cross-section and 14 metres high, stand on piled foundations. They support the trusses and ensure the horizontal stability of the entire building. The columns are integrated into the side towers, which shelter the entrance halls as well as the staircases and lifts providing access to the office floors.

Offices above the water

The horizontal ‘beam’ houses two office floors with floor-to-ceiling glazing, extending at either end into spacious terraces offering panoramic views of the city of Temse, the Scheldt Bridge and Scheldepark. Both office floors are accessible via the staircases and lifts in the support columns. They are connected by two external secondary staircases at the centre of the clear span. The building services rooms are located in the old pump room near the northern column, while the car parks and archive rooms are at the foot of the southern column.

The added value of BIM

Delivering a construction project on this scale requires everyone involved, from design through to construction, to bring a high level of expertise, flawless communication and tight coordination. Today, all this is made easier by BIM (Building Information Modelling). At the client’s request, Vorsselmans modelled its various interventions using Schüco aluminium systems. The curtain walls, sliding doors and their infill panels were also modelled in 3D, enabling architect Binst and Aertssen, which was responsible for manufacturing the steel frame, to check all connections, fixing points and other details before construction began.

Numerous parameters were added to the model, and everyone had access to the most up-to-date information in real time at all times. According to architect Binst, HQ, short for ‘Headquarters’, can also refer to the ‘High Quality’ required for this type of project.

‘Flexible’ Schüco façades

All external window systems were selected for their high resistance to heavy loads (the weight of the glazing and wind loads), as well as their high level of insulation, compatible with a passive building. The office façades feature triple glazing supported by a Schüco FWS 60.SI curtain wall system. The office façades are clad in Schüco curtain walls. Alongside the large glazing units, the main challenge on site was the high degree of flexibility in the steel frame. A solution therefore had to be found that would allow the façades to accommodate movement in the 72-metre clear span.

From the outset, the manufacturer Vorsselmans, working with its supplier of Schüco aluminium systems, opted to integrate an aluminium rail the same depth as the ceiling. This profile, a glass balustrade system with no visible profile, has a deep clamping groove that, in this case, allows movements of several centimetres in the frame without affecting the glazing or risking glass breakage.

The terraces at either end of the offices are accessed via Schüco ASS 70.HI sliding doors. The vertical glazed strips in the entrance towers were made using the Schüco AOC 60 ST.SI system (= Add On Construction Steel). Here, the horizontal aluminium profiles are fixed to an internal steel substructure, which absorbs the forces generated by the weight of the large one-piece glazing units and by positive and negative wind pressure.

Quote from Luc Binst, Binst architects

“A company’s administrative centres serve a representative function and call for architecture that supports and strengthens the company’s image and mission. We see the search for the design of an administrative centre as an honour that inspires us to strive for added value, inspiring individuality and architectural identity.”

Quote from Gert Hoefnagels, project manager

“After the shipyard went bankrupt, operations at the dry dock ceased. But by building our headquarters 20 metres above water level, we are keeping all options open for the dock to be repurposed or reused in the future.”

Project details

•    Project: Construction of the Cordeel contracting company’s administrative centre
•    Location: Temse (Belgium)
•    Client: Cordeel Groep NV
•    Architect: Binst Architects
•    Engineering firm: Ney + Partners
•    Façade contractor: Vorsselmans NV
•    Schüco systems: Schüco FWS 60.SI, Schüco ASS 70.BE, Schüco AOC 60 ST.SI

Schüco systems used

Schüco FWS 60.SI curtain wall

The FWS 60.SI curtain wall system (Façade Wall System, SI for Super Insulation) consists of vertical and horizontal mullions and transoms with a visible width of 60 mm. Its glazing rebate depth allows large glass units to be installed, with a maximum weight of 1,080 kg and a glass thickness of 68 mm. The system’s Uf value (U-value of the frame) is 0.7 W/m2K, making it suitable for passive buildings. Its air permeability and resistance to driving rain achieve classes AE and RE1200 respectively. The most robust profiles, fitted with internal reinforcements, have a static value of more than 7,483.6 cm4 (aluminium equivalent). The Schüco FWS 60.SI façade also has a C2C Silver environmental certificate.

Schüco AOC 60 ST.SI curtain wall

The AOC 60 ST.SI curtain wall system is similar to the FWS 60.SI, except that the inner load-bearing profiles have a flat underside and can therefore be mounted on support profiles made from another material, such as wood or steel. In this case, the horizontal transoms are fixed to internal steel supports, which bear the weight of the large windows and the wind pressure acting on them. The Uf value is 0.8 W/m2K, and both resistance to driving rain and air permeability meet class RE1350.

ASS 70.HI sliding doors

The ASS 70.HI sliding door has a Uf value of 2.0W/m2K and allows sliding panels to be manufactured up to 3 m wide and 3 m high. The sliding panel, with a construction depth of 70 mm, is suitable for windows weighing up to 400 kg and with a maximum thickness of 50 mm. The flat-section frame profile can be easily integrated into the floor, removing all obstacles at the transition between indoors and outdoors and thereby improving user comfort.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.