Student accommodation delivered in record time

Text Trees AccouImage MARKLAND architecten, Klaas Verdru

Student accommodation delivered in record time

An impressive student accommodation complex has risen in a short time along Burgemeester Vercruysselaan in Kortrijk. The Wing consists of two mirrored blocks connected to each other. “By opting for an H shape, we were able to make the most of the available space,” say the architects. A smart design and carefully devised planning by the main contractor made it possible to complete the building in just one year.

Kortrijk city centre has recently gained 172 student rooms. Residents have spacious, furnished rooms with their own bathroom, microwave and mini-fridge. They meet in shared kitchens in the central space connecting the two blocks. The lower half of the building’s eight storeys is underground. This design ensures students’ privacy and limits overlooking by passers-by. The lowest storey is arranged as a shared area with two functions. Architect Heleen Decuypere of MARKLAND architecten: “Our vision was to create both a proper relaxation area with sofas and a pool table, and a room where residents can study together. Both spaces open onto a semi-underground patio, complete with benches built into the steps up to ground level. The top storey of one block contains a partially covered roof terrace that is accessible only to students. The view over the city of Kortrijk is an added bonus.”

Most floors contain 28 student rooms and two shared kitchens.

Compact design

Kortrijk-based MARKLAND architecten drew up the design for client Kortrijk Student House. The site masterplan called for five identical blocks, spaced equally apart. In the first phase, two blocks were linked in an H shape. By positioning the stairwell and lift in the centre of the building and surrounding them with dead-end corridors lined with rooms, The Wing accommodates 28 student rooms on each floor. Heleen Decuypere: “At the client’s request, each student room was given its own bathroom. Everything has been designed to minimise wasted space without compromising on comfort. Each room has its own walk-in shower.    

Considerable attention was paid to the window detailing to achieve the desired architectural effect. The fixed glazed section has a window seat below it inside the room. Opening panels beside the fixed window create a playful effect on the façade, as they are randomly mirrored.”

In addition to the building’s spaciousness, speed of construction was also important. This had a particular impact on the choice of materials. “We used precast concrete, which not only saved time but also allowed us to use standard-sized windows. The dimensions were fixed to the millimetre, so we could order the windows before the walls were built.”

Precast concrete made rapid construction possible.
The distinctive window detailing defines the appearance of the façade.

Smart planning

The construction team had a year to complete the building inside and out. Main contractor Govaere is no stranger to a challenge and managed to deliver The Wing on time thanks to smart planning. Project manager Hugo Claeys: “We started construction on 1 June 2022, with handover scheduled for 1 August 2023. Deduct the construction holiday and you are left with a tight twelve months. Alongside our choice of materials, we relied above all on a few creative planning measures.”

The ventilation and electrical services were cast into the concrete slab, allowing some of the building services work to be carried out during the shell construction phase. “The time you lose in formwork for the concrete slab is more than recovered during the finishing phase,” says Hugo Claeys. “The external joinery was installed before the façade brickwork, allowing us to make the shell wind- and watertight sooner. Installing the external joinery early, together with temporary sealing of the service shafts above the third floor, meant we could start the interior finishing sooner. The bathrooms were painted before the sanitaryware was installed, allowing the painters and building services teams to work more efficiently. By thinking carefully about the sequencing in advance and monitoring the work daily, we were able to hand over The Wing as planned in summer 2023.”    

PROJECT DETAILS

Client Kortrijk Student House (Kortrijk)
Architect MARKLAND architecten (Kortrijk)
Main contractor(s) Govaere (Kuurne)

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.