Edenya: an atypical, dynamic construction site calls for precision and creativity
Text Philippe SelkeImage Yvan Glavie, Pairi Daiza, Dherte

A project management team of around 15, as many as 400 people working on site at the same time, concrete works on eight different levels beneath an imposing glass roof, and dozens of smaller work zones … It is clear that building the world’s largest tropical greenhouse was no small undertaking. It required intensive preparation, close involvement and meticulous coordination between all the parties involved. Together with main contractors Dherte, CIT Blaton and BPC Group, who pooled their strengths and tackled the work with great enthusiasm, we look back on an exceptionally complex, one-of-a-kind project that took no less than three years to complete.
Originally, the contract awarded to the temporary joint venture formed by the three main contractors covered the entire shell and core, including hotel rooms (some of them underwater or integrated into rock faces), reception areas (restaurants, terraces, lobby and public spaces), technical rooms for the sophisticated systems and animal care facilities, pools for different species (sharks, manatees, etc.) and a river running through the building, as well as numerous underground structures and the retaining wall supporting the greenhouse.
However, while work was in full swing, the JV was also entrusted with an additional task: coordinating the specialist services and fit-out packages. Pairi Daiza remained responsible for certain packages and specific finishes (earthworks, planting, pool waterproofing, artificial rockwork, habitat fit-out, etc.), with the relevant trades managed by technical director Jérémy Lannoy and his teams. This ‘dual coordination’ required intensive consultation, particularly to free up work zones and manage access for the final fit-out (ground cover, lighting, etc.).

Organisational and logistical complexity
The glass roof was installed first, in square modules of 2,500 m² (50 x 50-metre sections), allowing work inside to begin at an early stage without waiting for the roof to be fully completed. Christophe Cardinael, CEO of Dherte, a long-standing trusted partner of Pairi Daiza, says: “We couldn’t afford to wait until the glass roof was fully installed before starting work. We completed the foundations and lower sections of the landscape to be created one section at a time, until the work zone below was completely clear.”
The clear height of around 20 metres and the tiered layout, with as many as eight different levels, made it necessary to use mobile cranes with limited boom reach. As these are slower than tower cranes, this called for tight planning. Managing plant movements on site became increasingly complex as the 4-hectare greenhouse took shape: stabilising access roads, avoiding vulnerable areas such as pools that had already been poured or certain planted areas, and coordinating simultaneous operations …
Cédric Vande Moortele (BPC Group), project manager for the JV, says: “A member of our Methods and Planning department worked alongside our site teams every day to manage this organisational and logistical complexity on the ground. Managing access roads and storage areas was crucial. This included temporary ramps, built and removed every day to allow the necessary plant and deliveries to move around, right up to the final week of the construction period. The success of this delicate operation depended, of course, on the full commitment of the teams involved, and that was certainly there.”


A dynamic site with organic forms
Éric Doff-Sotta, CEO of CIT Blaton, which was no stranger to working at Pairi Daiza after completing The Land of the Cold, says: “The Edenya project was exceptionally complex, particularly because of the natural forms that had to be recreated. Many structures, such as the caves, were far from conventional, requiring atypical formwork and reinforcement to be designed. This was initially done by the site managers themselves, after which the engineers involved validated everything.”
The organic design and lack of repetition also limited the potential use of prefabrication, particularly in areas visible to the public. The project also includes a ‘hidden’ section almost as large as the visible area, housing imposing technical systems for animal care, climate control, ventilation and water management.
The project was also dynamic in the sense that it evolved in real time, with regular design changes requiring the site teams to be responsive and flexible. Daily discussions with Pairi Daiza and the other parties involved made it possible to adjust schedules where necessary and head off potential problems.

A success with a strong human dimension
The technical and logistical-organisational complexity of building Edenya presented a huge challenge, but was also a source of motivation and pride. Project managers, site staff, machine operators … everyone showed the necessary ingenuity, teamwork and professionalism to bring this iconic project to a successful conclusion. The three main contractors pooled their material and human resources, with the complementary skills of the people involved proving key to success. “The collaboration was excellent, and grew even stronger at more challenging moments, so that over time we became one big family. We can therefore look back with every justification on a particularly successful construction project,” concludes Christophe Cardinael.

Question about this story? Ask your question
Wie aan Edenya werkte
- dakstructuurForzonMentioned in Reynaers Aluminium demonstrates its technical expertise at Edenya (Pairi Daiza) with a tropical greenhouse on a global scale
- main contractorDherteIn this story
- main contractorCIT BlatonIn this story
- main contractorBPC GroupIn this story
- ClientPairi Daiza (Brugelette)Mentioned in Pairi Daiza unveils the world’s largest tropical greenhouse
- ArchitectSilent Architecture (Schaarbeek)Mentioned in Pairi Daiza unveils the world’s largest tropical greenhouse
- Hoofdaannemers ruwbouwTM DherteMentioned in Pairi Daiza unveils the world’s largest tropical greenhouse
- Hoofdaannemers ruwbouwSanctuary (Brussel)Mentioned in Pairi Daiza unveils the world’s largest tropical greenhouse
- installatie van de techniekenImtech NaninneMentioned in Fabric ductwork ensures optimal air distribution in new tropical greenhouse
- engineering consultancyTPF EngineeringMentioned in Fabric ductwork ensures optimal air distribution in new tropical greenhouse
- beglazingsspecialistAGC Glass EuropeMentioned in Unique glass roof for the world’s largest tropical greenhouse
- verlichtingssysteem SHUFFLESchréderMentioned in Multifunctional, discreet lighting enhances the visitor experience at Pairi Daiza
Keep following this
Get an email when a new story is published. No account needed.
- ProjectEdenya
- SubjectAcross borders
- CompanyDherte
- CompanyCIT Blaton
- CompanyBPC Group



















