Antwerp

Successful, sustainable regeneration almost complete

Text Els JonckheereImage AB-Eiffage

Wonen en werken worden verenigd op de voormalige Inofer-site.
Wonen en werken worden verenigd op de voormalige Inofer-site.

By early 2026, the large-scale regeneration of the former Inofer site near Mechelen station will be complete. Alongside two new, interconnected office complexes, ‘Malt’ also comprises fourteen flats and ten houses. The centrepiece, however, is the conversion of the existing Socaré building into offices where the spirit of its industrial past remains tangible. This successful regeneration demonstrates that vacant, undervalued sites can indeed be transformed into vibrant, sustainable and multifunctional urban neighbourhoods.

The former industrial site on Postzegellaan had long been an eyesore for the people of Mechelen. The location, once a hive of activity, had gradually become a site that exuded nothing but desolation and decay. Given that this was incompatible with the many improvements taking place in the station district, a thorough regeneration was the obvious way forward. Eventually, developers PSR and Codic joined forces to make it happen. The result was a highly ambitious project involving several architects, with AB-Eiffage responsible for the structural works and coordination of the other contractors. 

“The developers’ aim was to create a new urban district where people could live and work in a mix of heritage and new buildings,” says Raf Boogers, project manager at AB-Eiffage. “It had to be delivered in an exceptionally sustainable and future-focused way, as the investors were determined to achieve BREAM Excellent certification. It was therefore decided to heat and cool the buildings using a district heating network. The project also makes extensive use of ecological materials, such as FSC-certified timber. Smart mobility solutions are another feature: thanks to an underground car park of more than 10,000 m², the site is entirely traffic-free. Last but not least, the site will feature extensive greenery, with indoor and outdoor spaces for relaxation.”

The rest of the site is being developed with high-quality homes to suit every type of family.

A reminder of the industrial past

All the old buildings were demolished to make way for the new ‘MALT’ urban district, with the Socaré building retained. “With this renovation, the developers wanted to keep the memory of the industrial past alive,” says Raf Boogers. “That is why the exterior has been fully restored. Two additional storeys have also been added. Built using a steel frame and finished with a glazed aluminium façade, this extension blends seamlessly with the building’s distinctly Brutalist character.”

Inside, the floor slabs and walls were demolished to transform the building into a future-focused, sustainable office complex with a usable floor area of 6,128 m². The first companies are expected to move into the refurbished building by the end of February 2026. It combines an industrial look and feel with the highest levels of comfort.”

Two new office complexes as well

The additional storeys provide a seamless link to the new office complexes built alongside Socaré, which have been finished in a similar way. “Specifically, there are two volumes connected by a glass atrium,” explains Raf Boogers. “The building has six storeys on the street side, while the height is limited to four storeys towards the residential area. Together, they offer a usable area of 10,281 m², including the underground car park and plant rooms. The offices have a conventional fit-out, with a raised floor and climate ceilings. We are now putting the finishing touches to the project, with handover scheduled for the end of November 2025.”

Not just a place to work, but to live too

The rest of the site is being developed with high-quality homes to suit every type of family. In addition to two apartment buildings containing four and ten flats respectively (760 and 1,100 m²), there are also two groups of five houses. “These have been built using different types of brick,” continues Raf Boogaerts. “This gives each home its own distinctive character, while also creating a link with the renovated Socaré building. All the homes should be ready by the end of February 2026 at the latest. Thanks to the exceptionally green setting, sustainable heating and cooling, and easy access by car and public transport, the developers had little difficulty selling the homes.”

The façade of the Socaré building was retained, with additional storeys added.

A showcase for post-tensioned concrete

The project was right up AB-Eiffage’s street. “Once again, we were able to demonstrate that we can deliver large, complex projects within a relatively short timeframe,” says Raf Boogers. “And without compromising on quality or site safety. MALT also showcases the strength of our group. Our sister company PIT-Eiffage carried out the renovation of the Socaré building, while Reynders-Eiffage was responsible for manufacturing, supplying and installing the interior finishes. Technically, the project is also notable because it demonstrates the benefits of post-tensioned concrete, which makes maximum use of precast elements. This construction method has many advantages: there is no need for formwork, long spans are no problem, the concrete offers high strength, and the use of lightweight cables reduces weight by 35%. The result is a significant saving in concrete and steel.”   

PROJECT DETAILS

Client PSR Brownfield Developers (Aalst) and Codic (Brussels)

Architects Jaspers-Eyers Architects (Brussels, Leuven, Hasselt), Sculp Architecten (Antwerp) and Callebaut Architecten (Drongen)

Main contractor(s) AB-Eiffage (Antwerp)

Een zakelijke vraag aan Callebaut-architecten? Get in touch

Wie aan MALT werkte

  1. property developerPSRMentioned in Excavation works begin on MALT urban regeneration project
  2. developerCODICMentioned in Excavation works begin on MALT urban regeneration project
  3. property developerTrigintaMentioned in Excavation works begin on MALT urban regeneration project
  4. ArchitectCallebaut ArchitectenIn this story
  5. ClientPSR Brownfield DevelopersIn this story
  6. ArchitectJaspers-Eyers ArchitectsIn this story
  7. ArchitectSculp ArchitectenIn this story
  8. Main contractorAB-EiffageIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectMALT
  • SubjectAntwerp
  • CompanyCallebaut-architecten
  • CompanyPSR Brownfield Developers
  • CompanyJaspers-Eyers Architects
  • CompanySculp Architecten
  • CompanyAB-Eiffage
Share this article

Advertisement

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.