Large-scale industrial site completed in record time
Text Tim JanssensImage Frank Abbeloos

In just over a year, delivering a 5-hectare industrial site with around 25,000 m² of external storage space, a 13,000 m² production hall and an adjoining office building is an achievement to be reckoned with. Stadsbader pulled it off in the Port of Ghent, where it built a Flemish facility for the Walloon Brabant steel producer Armasteel. “Challenging projects like this are right up our street,” says project manager Ruben Raeymaekers.
Founded in 1971, Armasteel specialises in cutting, bending, prefabricating and installing reinforcing steel to order for all types of construction and infrastructure projects. To consolidate its strong market position, the company set its sights on establishing a facility in Flanders. It approached BVI.EU, which proposed a bespoke business complex with minimal environmental impact in the Port of Ghent. It was the perfect location, as Armasteel wanted to organise most of its steel deliveries by sea. The search for a contractor capable of building a substantial bespoke facility comprising production and office space, as well as laying thousands of square metres of concrete external paving, naturally led to Stadsbader.

Vertical integration as an asset
“The first phase of our contract involved handing over the new business premises watertight and weatherproof,” says Ruben Raeymaekers, project manager at Stadsbader. “The large hall has a precast concrete beam-and-column structure, supplemented by horizontal and vertical steel bracing. The façade sections above the concrete plinths are clad in dark grey steel sandwich panels. The adjoining office building was somewhat more complex from a structural perspective. Its load-bearing structure combines steel and concrete, with a steel truss used to create a large projecting upper floor. Installing this element was no easy task, but thanks to the expertise of our skilled teams, the work went smoothly. We lifted the components into position using heavy-duty cranes and then completed the assembly.”
“The enclosed ground-floor façade sections are clad in white concrete sandwich panels, which are also used on the projecting canopies between the different floors. Most of the remaining façade consists of curtain walling with extensive glazing. We were also responsible for the landscaping, and almost all the precast concrete elements were manufactured in-house at our Van Maercke Prefab production facility and installed by our own precast assembly teams.” Stadsbader’s strong focus on vertical integration once again proved a valuable asset for the client.

Tight deadlines
The schedule for this project was exceptionally tight. Armasteel wanted to start using its new hall as soon as possible. “Planning is always a critical factor in industrial construction, but in this case the timescale was extremely demanding,” continues Ruben Raeymaekers. “Production was due to start in March 2024, which meant the hall floor had to be poured in December 2023. The hall’s precast concrete load-bearing structure was erected by two installation teams, each using a heavy-duty crane. The work went very smoothly, and the structure was standing within just over a month. The roof and façades were then completed at pace. Finally, the hall floor was poured in six phases of approximately 2,000 m², at a rate of one phase per week. That, too, went extremely well, much to Armasteel’s satisfaction.”
“Despite the poor weather, we managed to meet the deadline,” explains Ruben Raeymaekers. “The site being operational since March had a significant impact on the rest of our work. By then, 5,000 tonnes of steel had been delivered to the site, so we had to plan the installation of the top layer of the concrete external paving carefully. We are very pleased that everything went so smoothly. Challenging projects like this are right up our street, thanks to the speed and flexibility we can bring to bear across all our divisions.”
Een zakelijke vraag aan Stadsbader? Get in touch
Who worked on it
- ClientBVI.EU (Kontich, Waver)
- Construction coordinatorDelta Sierra (Roosdaal)
- Architectmortelmans van tricht architecten (Antwerpen)
- Main contractor for structural works (weatherproof and watertight) and external worksStadsbader (Harelbeke)