Brouwerij Roman in Oudenaarde, one of the country’s oldest family breweries, has embodied craftsmanship for centuries. Today, the current generation of managing directors is taking the next step in this story. An ambitious masterplan is preparing the brewery for the future, while respecting its rich history and unique setting.

The project focused on reusing space and materials, optimising daylight and managing water.

Over the centuries, the brewery complex grew into a tangle of buildings around a central courtyard. It was once a place where horses and carts brought in ingredients and took away beer. In recent decades, the site has focused mainly on logistics and storage. The landscape around the brewery, the hills of the Flemish Ardennes, remained largely out of sight. The need for a new brewhouse, additional storage capacity and lower energy costs, combined with the desire to give the beer experience greater prominence, led to the development of a masterplan that reimagines the entire
site.

Brewing vessels and fermentation tanks sit on a robust concrete table structure.
Enlarged window openings were emphasised with concrete surrounds.

Maximum reuse of existing buildings

The starting point was to retain and repurpose the existing commercial buildings. Unnecessary volumes were stripped out, and the central courtyard once again became the heart of the brewery. The first phase involved transforming the old logistics wing into a new brewhouse. Its location makes the wing a natural extension of the bottling hall and storage areas. “The building’s linear layout is perfectly suited to the brewing process, which follows a sequence from the brewing vessels to the bottling hall. Large façade openings and rooflights make this process visible from the courtyard and give the brewery a new face,” says Kris Buyse, architect and managing director at 360 architecten.

Functional technology and an engaging experience

The original section of the wing served as the starting point. Brewing vessels and fermentation tanks sit on a robust concrete table structure, while the ground floor accommodates technical installations. A lightweight steel structure supports the renovated roof planes, where generous rooflights bring in abundant daylight. The visitor route also plays a leading role. From the courtyard, beer lovers follow the covered loading bay past the new brewhouse and fermentation tanks to a viewing platform above the bottling hall. This creates a loop that brings together the brewery’s history, the landscape and the contemporary brewing process.

Respectful interventions

The façade alterations were carried out with great respect for the building’s existing character. Enlarged window openings were emphasised with concrete surrounds, while additional first-floor windows strengthen the relationship between the interior and the courtyard. The modernised gateway marks a new chapter in the history of Brouwerij Roman. A double steel beam supported by two columns forms a contemporary entrance to the future, both functionally and symbolically.

Functionality, experience and sustainability reinforce one another.

Sustainability as a foundation

Alongside functionality and aesthetics, sustainability was a guiding principle. The new brewhouse combines a high-performance building envelope with carefully planned circulation routes and an efficient structural shell. The project focused on reusing space and materials, optimising daylight and managing water. Rainwater storage and a treatment plant ensure responsible water use, while heat from the brewing process is recovered.

Strong collaboration

The project was delivered through close collaboration between several parties. Engineering consultancy Mouton carried out the structural studies, and contractor Mathieu Gijbels was responsible for the construction. The result is a project of the highest architectural and technological standard. With these renovations, Brouwerij Roman opens a new chapter in its centuries-old history. The masterplan combines respect for the past with a vision for the future. Functionality, experience and sustainability reinforce one another. The site has once again become a lively, distinctive whole, embedded in the landscape of the Flemish Ardennes and ready to welcome visitors and beer lovers to a setting that brings together authenticity and innovation.        

The central courtyard has once again become the heart of the brewery.

GVG Beton: Concrete and foundation works

GVG Beton carried out the concrete and foundation works at the Brouwerij Roman site. The family-run company Van Gaeveren, now a well-established name in the sector, combines decades of experience with strong growth momentum. For this project, the team took on a particularly challenging task: constructing a concrete wall with a sinusoidal profile, a structure not available off the shelf. Working closely with the architects, the team sought to achieve the right wave pattern. Following a trial phase at another site and a thorough inspection by the client and designers, the work was given the go-ahead. “The whole team was delighted with the result,” says project manager Andy Van Gaeveren. “This project shows how important flexibility and trust are. Working with the client and architect, we were able to make the right choices at every stage.” All the work was carried out in phases using in-situ concrete. The result demonstrates the reliability for which GVG Beton is known: quality across residential and industrial projects, large and small.

TECHNICAL DETAILS

Client Brouwerij Roman (Oudenaarde)
Architect 360 architecten (Gent)
Main contractor(s) Mathieu Gijbels (Oudsbergen)

Question about this story? Ask your question

Wie aan Brouwerij Roman werkte

  1. cloudplatform Trimble ConnectTrimbleMentioned in Brouwerij Roman ready for the future with 3D BIM software
  2. contractorMathieu GijbelsMentioned in Brouwerij Roman ready for the future with 3D BIM software
  3. architect360 architectenMentioned in Brouwerij Roman ready for the future with 3D BIM software
  4. stabiliteitsbureauMoutonMentioned in Brouwerij Roman ready for the future with 3D BIM software
  5. stabiliteitsstudiesStudiebureau MoutonIn this story
  6. beton- en funderingswerkenGVG BetonIn this story
  7. clientBrouwerij RomanIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBrouwerij Roman
  • SubjectEast Flanders
  • CompanyStudiebureau Mouton
  • CompanyGVG Beton
  • CompanyBrouwerij Roman
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.