Flemish Brabant

Sustainable construction with strong local roots

Text Bertrand LafontaineImage Pellikaan Bouwbedrijf

TECHNISCHE FICHE Bouwheer Gemeente Zemst Architect czaar architecten (Leuven) en Studio Klein Brabant (Bornem) Hoofdaannemer(s) Pellikaan Bouwbedrijf (Zaventem)
TECHNISCHE FICHE Bouwheer Gemeente Zemst Architect czaar architecten (Leuven) en Studio Klein Brabant (Bornem) Hoofdaannemer(s) Pellikaan Bouwbedrijf (Zaventem)

With the new Sporthal Den Turfput, Zemst has gained more than just extra sports facilities. The hall has become a hub in Leibeekpark, where sport, nature and culture come together. “The collaboration between the construction and design teams really contributed to the excellent end result,” they say.

The new sports hall was fitted between the football pitches, Leibeekpark and community centre De Melkerij. The architecture, designed by czaar architecten and Studio Klein Brabant, with landscape integration by Sweco, strengthens this threefold context: sport, greenery and culture. New public spaces have been created around the building, including an extension to the events square and a restored stream valley. Thanks to its low, undulating form and semi-intensive green roof, the building blends visually into the landscape. Only at the entrance, which also houses the dance studio, does the roof rise in an inviting gesture.

The sports hall makes optimal use of passive solar gains, while natural light contributes to users’ wellbeing.
The new sports hall was fitted between the football pitches, Leibeekpark and community centre De Melkerij.

Sustainable materials and refined finishes

For main contractor Pellikaan and project manager Stijn Biesemans, the construction of Sporthal Den Turfput was an opportunity to put their expertise in Design & Build projects fully to use. “What sets Den Turfput apart is the careful choice of materials and the quality of the finish. We chose sustainable materials that also convey warmth and quality,” says Stijn Biesemans. The façade of durable ash timber, combined with a beige concrete plinth and black external joinery, subtly references De Melkerij’s earthy palette. Inside, the combination of exposed brickwork, fibre ceilings and terrazzo tiles creates a high-quality feel. “The Municipality of Zemst really opted for quality. Every detail is just right.”

Pellikaan carried this attention to detail through to the smallest finishing touches. Biesemans recalls adjusting the length of the timber entrance columns to match the slope of the site, so that they aligned seamlessly with the paving outside. 

“Because we also carried out the external works, we were able to coordinate everything precisely,” he says. “That makes the site feel like one coherent whole. At Pellikaan, we also take full responsibility for managing the project for our client, from design through to aftercare. We handle the planning application, liaise with the fire brigade and planning authorities, and keep a close eye on the budget and schedule. This gives the client peace of mind at every stage.”

Energy-efficient, gas-free building

Den Turfput also sets an example in terms of sustainability. The sports hall is entirely gas-free and is heated and cooled by two heat pumps. The building has an E-level of 18, well below the required standard. “That is thanks to the carefully considered insulation, airtightness and 280 solar panels on the roof,” explains Stijn Biesemans. “The municipality deliberately chose to more than double the number of PV panels.”

The abundance of daylight, entering through rooflights, windows and polycarbonate façades, makes the building more energy-efficient and creates a pleasant indoor climate. The sports hall makes optimal use of passive solar gains, while natural light contributes to users’ wellbeing. “It’s not just a functional building,” says Biesemans, “but a place where people enjoy spending time.”

The main sports hall can be divided into three smaller halls, while the dance studio and changing rooms can be used separately.

Smart layout and construction methods

The design team opted for an intelligent floor plan that allows flexible use. The main sports hall can be divided into three smaller halls, while the dance studio and changing rooms can be used separately. “Football club FC Zemst was given a separate, lockable area,” explains Stijn Biesemans. “The changing rooms were designed so they can be split in two. This creates four changing rooms instead of two, a smart solution that doubles capacity.”

“Our construction method also helps,” he says. “The prefabrication process is fully integrated with BIM. Every component, from beams and columns to complete walls, is designed digitally. Our precast manufacturers link their production drawings directly to the BIM model, which is connected to the production hall.

This means production can start before the first spade has even gone into the ground. That makes for exceptionally fast delivery, with fewer risks, errors and less waste.”

The changing rooms were designed for flexible use.

Precision logistics and teamwork

The fast delivery was no coincidence, but the result of a well-prepared and closely monitored site. Work began in June 2024 and was completed exactly one year later. “Precisely as planned,” smiles Stijn Biesemans. Only the transport of the 33-metre roof beams required special attention. “We had to remove road signs to allow the lorries to reverse all the way to the site. The beams arrived at night and by midday they were all in place. It took intense concentration and teamwork.”

That strong collaboration extended to the site itself. Pellikaan worked with the same two-person team from start to finish: Stijn Biesemans and his site manager. “Because we prepared and monitored everything together, no information was lost. That added enormous value and ensured consistency in the work.”

Local roots and personal pride

This project held special significance for Stijn Biesemans. “I live 2 kilometres from the site,” he says. “From the outset, I said: this is a project I definitely want to do. You know the people, you know the place. That builds trust.” This local connection led to close collaboration with the football club, whose chairman knew the underground services by heart. “He knew where everything was. That kind of local knowledge makes a big difference.”

That close connection also makes the pride tangible. “I still pass by a few times every week,” says Biesemans. “Every time, I think: I’ve really been able to build something here for my own municipality.” For him, Sporthal Den Turfput is not only an example of sustainable architecture and efficient construction, but also of commitment and ownership. “Of all the projects I’ve worked on, this has been the most successful in every respect,” he concludes.    

Ecoworks: Pitched green roof

Ecoworks is a pioneer in the design, construction and maintenance of green roofs, roof gardens, green façades and swimming ponds. Since 2006, the company has been exploring ways to give nature a permanent place in the city and to make water and greenery work together. Today, the team looks beyond greenery on buildings alone, exploring how nature and water can contribute to a more sustainable living environment. For Sporthal Den Turfput in Zemst, Ecoworks designed the pitched green roof, which always requires additional study. “Our slogan is ‘Create Nature’,” says garden designer and operations director Yannick Lepage. “We create greenery where it would not normally be possible, on roofs, slopes or technical structures. The roof is quite steep on the street-facing side of the sports hall. We used an approach similar to Asian rice terraces, with panels that distribute the weight in steps and retain rainwater. Above them is a herb-rich sedum mat, secured with a root net to prevent erosion.” Ecoworks also continues to monitor the green roof after completion. “We have a maintenance contract, because a green roof is alive,” says Lepage. “It changes with the seasons and therefore needs ongoing care. This summer, we found that it needed a little more irrigation. We’re monitoring it and making adjustments where necessary. It’s wonderful to see how the roof now forms a seamless whole with the surrounding landscape.”

TAC: HVAC-S

TAC was responsible for heating, cooling, ventilation and plumbing at Sporthal Den Turfput. “We were responsible for the entire HVAC-S package,” says Nathan Van Overloop, Chief Enabling Officer at TAC. “The sports hall was an interesting type of building for us, with major fluctuations in use. At quiet times, consumption is minimal, but after a training session, suddenly everyone is in the showers at once. The system needs to handle that peak perfectly.” Technically, the project was particularly innovative. “The sports hall in Zemst houses Carrier’s first installation in Belgium using the natural refrigerant R290,” says Van Overloop. “That’s propane, an environmentally friendly refrigerant, but this was the first installation of its kind in the country. It did cause some stress, as it was also a first for Carrier’s technicians.” The system can heat and cool at the same time, and is equipped with energy meters for each circuit. “This allows the municipality to monitor exactly how efficiently the system is operating. It’s a good example of how modern HVAC technology not only ensures comfort, but also actively contributes to a building’s sustainability.”

GEVITEC: Electrical installation

Gevitec was responsible for the entire electrical installation at the new sports hall in Zemst, from lighting and data cabling to fire detection and access control. “To put it bluntly, we did everything involving a cable,” says assistant director Andy Borghs. “Emergency lighting and fire safety systems also had to meet the latest standards in full. Inspections are strict, which makes it all the more important to get every detail right.” According to Borghs, the challenge was not only in the technical work, but also in coordinating between different parties. “Sometimes a client asks us to work with a new partner. For access control, for example, it was a company we didn’t know, but because we’re flexible, we made it work. That’s our strength: responding quickly and finding solutions together.” Collaboration with Pellikaan also went particularly smoothly. “The schedules were tight, but everything was kept on track,” says Borghs. “We know each other inside out, which creates a great deal of mutual trust. If they call today and ask us to be on site the day after tomorrow, we’ll be there.” Thanks to well-coordinated scheduling and open communication, the project was completed without any significant obstacles, just as it should be.

PROJECT SPECIFICATIONS

Client Municipality of Zemst

Architect czaar architecten (Leuven) and Studio Klein Brabant (Bornem)

Main contractor(s) Pellikaan Bouwbedrijf (Zaventem)

Een zakelijke vraag aan Pellikaan Bouwbedrijf nv? Get in touch

Who worked on it

Sporthal Den Turfput in Zemst

  1. main contractorPellikaan Bouwbedrijf
  2. architectczaar architecten
  3. architectStudio Klein Brabant
  4. hellend groendakEcoworks
  5. HVAC-STAC
  6. electrical installationGevitec
  7. ClientGemeente Zemst

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectSporthal Den Turfput
  • SubjectFlemish Brabant
  • CompanyPellikaan Bouwbedrijf nv
  • Companyczaar architecten
  • CompanyStudio Klein Brabant
  • CompanyEcoworks
  • CompanyTAC
Share this article

Advertisement

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.