Education

Ledeganck 2.0: proof that renovation pays off

De ramen van de toren werden vervangen door gezeefdrukt, zonwerend hoogrendementsglas en geïsoleerde sandwichpanelen.
De ramen van de toren werden vervangen door gezeefdrukt, zonwerend hoogrendementsglas en geïsoleerde sandwichpanelen.

It took no less than ten years to give UGent’s Campus Ledeganck a new look.

The brief was far from simple: to make the building sustainable, flexible and up to date while retaining as much of the original design as possible. A blend of creativity, expertise and vision resulted in an architectural concept that demonstrates how the future-oriented transformation of old and complex buildings can succeed. 

Campus Ledeganck is located on Karel Lodewijk Ledeganckstraat, close to Citadelpark in Ghent. The complex was built in 1969 to a design by architect Jules Trenteseau. With its façade of grey enamelled glass panels and clear glass, the twelve-storey tower was a striking feature of Ghent’s skyline. “It made perfect sense to develop a renovation concept that respected the building’s original appearance,” says Petia Hanssen,
project architect at Abscis Architecten. “That sounds easier than it was. Ledeganck is the campus of UGent’s Faculty of Science. The client wanted a high-performance university building, including a contemporary laboratory concept that could expand and contract to meet the faculty’s needs.” 

A blend of creativity, expertise and vision resulted in an architectural concept that demonstrates how the future-oriented transformation of old and complex buildings can succeed.

In four phases

As Campus Ledeganck could not simply close its doors, the renovation was carried out in four phases. The ‘plinth’ of the tower building was tackled in 2010. “This is a rectangular low-rise section that provides a transition to the surrounding fabric of traditional building blocks,” explains Petia Hanssen. “It resembles a gatehouse and has 6+1 storeys. The plan was to accommodate several L3 containment laboratories in this volume, as well as offices, research laboratories, a caretaker’s residence and public toilets. The interior was therefore stripped back to the shell and then refitted to meet current requirements for safety, energy performance, fire evacuation … The exterior remained virtually unchanged: the existing white hardstone façade was cleaned, and the windows and joinery were replaced with higher-performance alternatives.” 

A colourful mosaic 

In the second phase, the four façades of the freestanding tower were renewed using a particularly original concept. Abscis Architecten decided to replace the existing windows with screen-printed solar-control high-performance glazing and insulated sandwich panels. “Instead of the former ‘grey with a light bluish tint’, we opted for a palette of grass-green shades,” says Petia Hanssen. “Using four types of glass, clear and opal, light and dark enamelled, created a mosaic based on Trenteseau’s original modules. At first glance, there is no discernible pattern on the façade. Yet it is laid out logically. Each parapet, column, floor or service shaft has an enamelled panel. All the other spaces have large windows with at least four clear-glass modules. In the evening, the pattern becomes clear as the clear and opal glass panels glow from within. This makes Campus Ledeganck even more prominent on Ghent’s skyline.”

Complete renovation

The tower was also stripped back to the shell. The existing structure was fire-protected and then finished with the new façade. The entire volume was subsequently refitted. The refurbished tower now houses three large practical teaching rooms, several research laboratories and a number of offices. Petia Hanssen: “Various climate rooms have been installed on the sixth floor. Thanks to the modular façade concept, they do not appear as blank patches on the exterior. The top floor has been designed as an internal outdoor space, filled with air-handling units and chillers.”

Campus Ledeganck now has a large number of new laboratories that can adapt to changing requirements.

Major phase 3

From 2015 to 2017, work was carried out on the volume along the campus’s south façade. The approach was the same: stripping back to the shell and a complete refit. “The existing curtain wall was replaced with a new one featuring large areas of anodised aluminium-framed glazing,” says Petia Hanssen. “This building also houses laboratories, as well as auditoriums and offices. New bicycle storage and plant rooms were fitted out at basement level. This phase was a major undertaking
because all the campus services were also renewed. In addition, an extensive network was installed to supply the laboratories with specialist fluids and gases. The exterior was also upgraded: the existing curtain wall was replaced with a new one featuring large areas of anodised aluminium-framed glazing. To make maintenance easier, a façade-cleaning system with cradles was installed on the roof.” 

Museum included

In the final phase, the former laboratories in the west wing were given a new purpose: the GUM or Ghent University Museum. “The university’s valuable collections are on permanent display on floors +2 and +3,” explains Petia Hanssen. “The fourth floor is for temporary exhibitions and also houses an events hall. New teaching rooms and student facilities have been fitted out on the ground and first floors. The fifth floor houses several laboratories and offices. This volume was also completely stripped back, with the exception of the cleaned natural-stone façade.

A distinctive appearance

A new rooftop volume was added to house the extensive ventilation plant. Petia Hanssen: “To ensure this additional volume would enhance both the building and its surroundings, we decided, in consultation with the city authorities, to build it as a translucent structure clad in polycarbonate panels. In the evening, it is evenly illuminated from within by three continuous horizontal lighting strips, one above the other. This gives the building a distinctive identity as a museum and secures its rightful place alongside the other visitor attractions in the area.”  

PROJECT DETAILS

Client UGent (Ghent)

Architect Abscis Architecten (Ghent)

Main contractor(s)
(phase 1) Vandenbussche (Aalter)

(phases 2-3) BAM Contractors (Brussels)

(phase 4) BAM Contractors (Brussels), De Mulder (Geraardsbergen) & Cegelec (Zwijndrecht)

Question about this story? Ask your question

Wie aan Campus Ledeganck werkte

  1. levering en installatieTEM TechniliftMentioned in Campus Ledeganck, Ghent | High-performance lifts for a renovated tower
  2. clientUGentIn this story
  3. architectAbscis ArchitectenIn this story
  4. main contractorVandenbusscheIn this story
  5. main contractorBAM ContractorsIn this story
  6. main contractorDe MulderIn this story
  7. main contractorCegelecIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectCampus Ledeganck
  • SubjectEducation
  • CompanyUGent
  • CompanyAbscis Architecten
  • CompanyVandenbussche
  • CompanyBAM Contractors
  • CompanyDe Mulder
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.