A striking feat of stability for KV Mechelen

Since the start of last football season, KV Mechelen supporters have been able to take their seats in a brand-new main stand. The theoretical expertise, technical capabilities and efficiency of structural engineering firm Stabilogics helped deliver this striking feat of structural engineering.
Great attention was paid to the detailing and construction of the new main stand at the AFAS Stadion in Mechelen. And rightly so, because as it supports the entire structure, the structural work is the most important element in ensuring the stability of the whole. “We started the design work in March 2018,” says Eddy Hermans, engineer and managing director of Stabilogcs. “Demolition work could not begin until after the final match of the 2017-2018 season, in mid-April. Given the ground conditions and the large foundations of the existing complex, this took a little longer than originally planned. The new structure consists of a prefabricated concrete frame with three cores incorporating the lifts and staircases. This carefully designed structure also made for rapid assembly.”

Building the steel support structure for the cantilevered section was no routine task either. No two trusses are the same height or length.
A balancing act
“The main challenge was to ensure the overall balance of the structure as effectively as possible. Thanks to the three cores, we were able to solve this problem fairly quickly. The floor slabs act as stability diaphragms, transferring the forces to the cores. As the structure is relatively long, expansion joints were needed to allow it to expand with changes in temperature. To ensure the joints could transfer forces, we used so-called ‘dowels’. This allows the forces to be transferred efficiently while the structure moves as it expands and contracts.”
Designing the roof structure also proved a balancing act, both literally and figuratively. Stabilogics had to take account of wind forces acting both upwards and downwards. Building the steel support structure for the cantilevered section was no routine task either. No two trusses are the same height or length. “This meant we had to calculate the potential load on each individual element. The load can be very high due to the combined effects of wind and winter precipitation, as the canopy is supported only at the rear of the stand. There, it is fixed to the concrete columns and to the column one bay further along.”

The new main stand at KV Mechelen under construction. Stability was a crucial consideration.
A logistical tour de force
The project also presented logistical challenges. Eddy Hermans: “We used three tower cranes during construction. Unfortunately, we had little room for pre-assembly. During the two previous phases, in 2015 and 2016, we had a little more space available. This time there was almost none, which meant everything had to be transferred directly from the trailer to the site. There was virtually no room for storage. Fortunately, we managed to complete everything successfully.”