A success story in the Venice of the North

De vele bomen in het park moesten koste wat kost behouden blijven op vraag van het Brugse stadsbestuur.
De vele bomen in het park moesten koste wat kost behouden blijven op vraag van het Brugse stadsbestuur.

Work on Bruges’ ’t Zand car park, which began in June 2020, is progressing at a brisk pace towards final completion. Despite the challenges along the way, all the tight deadlines were met. In short, this project is a real success story, delivered in close collaboration with Bruges City Council. Local residents were kept informed throughout through regular site visits, a timelapse, newsletters, an observation point and more. 

The entire car park sits on a gentle slope more than 120 metres long, following the original contours around the trees.

Three additional parking levels have been added beneath Bruges’ Koning Albert I Park, providing 365 extra spaces across an area of 18,000 m². The car park now has a total capacity of 1,932 spaces. During the works, contractor CIT Blaton had to address several challenges, including the surrounding natural environment, excavating thousands of cubic metres of earth and pumping out water with great care.

The extension of Bruges’ ’t Zand car park, which began in June 2020, was commissioned by Interparking.

70,000 m³ of earth, 800,000 m³ of water

More than 500 metres of slurry walls were installed to a depth of 24 metres, retaining both soil and water. The slurry walls also formed the car park’s external walls. In February 2021, no less than 70 000 m³ of earth was excavated. Given the size of the excavation and the high groundwater level, pumping out the water proved a real challenge. Jan Heyde, project manager at CIT Blaton: “Our main concern was that the discharged water should not negatively affect biodiversity in the nearby stream or pollute it. We therefore installed a water treatment plant (WTP) to capture all the excess iron and other pollutants. The water was also supplied with the necessary oxygen. In total, we pumped out 100 m³ per hour! That came to a total of 800,000 m³ over the entire duration of the works.”

12,000 m² of concrete floor slabs and four hundred prestressed beams were installed for the roof.

Construction at speed

The shell construction phase was completed in a record five months, thanks in particular to the three tower cranes installed in summer 2021. In this short period, 12,000 m² of concrete floor slabs and four hundred prestressed beams, each 16 metres high and weighing 16 tonnes, were installed for the roof. Jan Heyde: “Towards the end, the schedule was slightly disrupted and had to be adjusted daily because of coordination problems with deliveries from subcontractors and suppliers of the metal structures. The natural stone for the footpaths and wall cladding was also subject to significant delays. In these post-coronavirus times, unfortunately, this is more the rule than the exception.”

Three additional parking levels have been added, providing 365 extra spaces.

Special care for the trees

At the request of Bruges City Council, the many trees in the park had to be preserved at all costs. Once the ring road around the site was complete, the old access road to the car park could be demolished and ninety reinforced secant piles could be cast around a red beech that is several decades old. The entire car park sits on a gentle slope more than 120 metres long, following the original contours around the trees. Finally, 2,400 m² of footpaths were laid. Jan Heyde: “After the final checks before opening and inspections by the competent authorities, the extension to ’t Zand car park in Bruges opened to the public on 29 April. The official inauguration, which will also be attended by the city council, will take place shortly, once the park is complete.”    

By completing the project on time, the contractor pulled off a remarkable feat.

Question about this story? Ask your question

Who worked on it

  1. ClientInterparking (Brussel)
  2. ArchitectBOVAArchitects (Gent) en West 8 (Opwijk)
  3. Main contractor(s)CIT Blaton (Brussel)

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.