Broad construction and property sector joins forces to untangle planning permission bottleneck
Text and images Embuild Vlaanderen

Flanders faces many challenges in which the construction and property sector has a key role to play: delivering additional housing within the parameters of the construction shift, the energy-efficiency renovation wave, making our buildings and infrastructure climate-resilient, the urgent construction and reconstruction of roads, dykes, bridges and sewers, and their maintenance … Legally certain, robust and efficient planning procedures are a necessary precondition, but one that has yet to be achieved. This lack of legal certainty is paralysing and delaying many important initiatives. The Flemish government recognises this and has set up a mixed committee of experts, tasked with proposing procedural improvements by September.
The leading organisations in the construction and property sector, Embuild Vlaanderen, Bouwunie, BVS, NAV, the Orde van Architecten, BVA and ORI, welcome this move. “More than that, we are joining forces and presenting the committee and the government with a joint paper setting out practical solutions for every stage of the procedure, from the underlying regulations and pre-application discussions to the handling of appeals. As a sector, we are convinced that the contents of planning applications should also be reviewed,” says Caroline Deiteren of Embuild Vlaanderen.
The pendulum has swung too far
“The focus must therefore not be solely on appeal procedures at the end of the process. The pendulum has swung too far, with the sheer number of studies and site investigations required, as well as the level of detail demanded. These cost a great deal of time and money, and their added value can often be questioned,” says Olivier Carrette of BVS. “Unfortunately, obtaining planning permission today often means running a veritable obstacle course. Pre-application discussions regularly descend into unnecessary and time-consuming back-and-forth. The tangle of regulations and numerous local by-laws make planning applications extremely complex. And the (too) low threshold for lodging an appeal results in wasted time and money,” explains Jean-Pierre Waeytens of Bouwunie. “Conflicting policy visions at Flemish and local level are also a major cause of delays. This is a serious obstacle to the densification task,” says Steven Lannoo of NAV.
Kafkaesque planning procedures
From pre-application discussions and appeals to spatial planning and environmental regulations, the construction and property sector is putting forward proposal after proposal to end the Kafkaesque nature of planning procedures. The Flemish government is encouraging densification, yet applications for precisely these projects have the lowest chances of success. This is according to a study by KU Leuven. In Flanders, obtaining planning permission for a residential project of twenty units, including the preliminary process, takes an average of 28.5 months, or almost 2.5 years, in the best-case scenario. In the worst case, if an appeal is lodged with the Council for Permit Disputes, the average processing time is 65.5 months, or more than five years. Some projects, however, remain stuck in the process for seven to ten years.
Practical solutions
On the basis of an analysis of bottlenecks and a list of practical solutions, the sector now wants to work with the new mixed committee to get construction projects in Flanders moving again. The following are priority points from a more extensive list:
- Pre-application discussions: recognise the value of this stage by making agreements binding. It currently takes a great deal of time, yet many matters are later reversed in the process.
- Contents of planning applications: radical simplification is needed. The increasing volume, level of detail and complexity of the plans and studies required have gone beyond the bounds of common sense.
- Planning procedure: apply the “only once” principle to avoid repeatedly requesting information, whether mandatory or not. Extensive digitisation is also needed.
- Public consultation: ensure that not only opponents, but also businesses, associations and members of the public who support a project can have their say.
- Appeal procedure: ensure that only individuals and parties with a direct and personal interest can lodge an appeal, and provide additional staff to avoid months of delays.
- Densification policy: conflicting visions at Flemish and local level are causing major delays in the planning process. This makes the densification task almost impossible. A clear vision is therefore needed that transcends levels of government and brings order to the proliferation of local by-laws. There is also a need for “construction shift covenants” in which all levels of government and stakeholders endorse joint agreements and commitments.