Construction continues to be hit by price rises and material shortages

Lead times for construction materials are worsening, while price rises continue to accelerate. This is according to a survey by the Confederation of Construction.
Contractors are bearing more than half of the price increases, while in 41% of cases the bill is passed on to the client, though more often partially than in full. Notably, significantly more construction companies are now using a price revision clause: 54% in September, compared with 45% in June. Charging a daily rate is proving even more popular, and its uptake is rising faster. “Nearly half of respondents expect the federal government to classify these circumstances as exceptional, while there are also calls for greater solidarity throughout the construction supply chain,” says Robert de Mûelenaere, managing director of the Confederation of Construction.
The construction sector continues to grapple with material shortages and price rises. A survey by the Confederation of Construction, in which 204 construction companies took part, shows that lead times for construction materials have deteriorated slightly:
- In September, 62% of construction companies reported lead-time extensions of more than 2 weeks (compared with 60% in June), and 36% reported extensions of more than 4 weeks (compared with 31% in June).
- Lead-time extensions are most pronounced for timber and polyurethane insulation. More than one fifth of contractors even report extensions of over 2 months.
- For other insulation materials, more than 20% also report extensions of over 2 months.
Extended lead times are currently causing delays on 59% of ongoing contracts (compared with 52% in June). Construction companies are also facing price increases:
- 59% of contractors have seen increases of more than 15% since November 2020 (compared with 57% in June 2021 and 37% in March 2021).
- 32% have seen price rises of more than 25%, and 12% even report increases of over 50%.
- Price rises are greatest for timber, steel and polyurethane insulation.
Notably, expectations for the coming months regarding price rises and the supply of materials are not as bleak as they were in June, offering a modest glimmer of hope. Nevertheless, given the exceptional current situation, the Confederation of Construction has been recommending for several months that companies use a price revision clause or charge a daily rate. This helps ensure that contractors do not bear the full brunt of price increases, and that contracts are balanced, with both parties knowing where they stand. The sector federation notes, however, that price rises are still borne entirely by the construction company in 54% of cases, and by the client in 41%, more often partially than in full. At the same time, it is encouraging that the Confederation’s advice is being followed: 54% now use a price revision clause, compared with 45% in June. More and more construction companies are also charging a daily rate: 52% in September, compared with 37% in June.
The construction sector is above all calling for political recognition that these are “exceptional circumstances”, the survey also shows. This means that contractors should not have to bear all the risks, since the price increases are abnormal. The Confederation of Construction is discussing this with the federal government. At the same time, construction companies are calling for greater solidarity and dialogue throughout the construction supply chain, so that tensions around prices and lead times can be managed more easily.