Construction risks missing out on economic recovery due to materials crisis (supply problems and price rises)

The construction sector appears to have weathered the coronavirus crisis well. Order books are, on average, filled for almost 6 months.
However, a new crisis threatens the successful and timely completion of these orders. All contractors are facing price rises of between 15% and 50% or more. 8 in 10 construction firms are experiencing supply problems lasting 2 to 4 weeks or more. “We must be careful not to move from the coronavirus crisis into a materials crisis,” says Robert de Mûelenaere, managing director of the Confederatie Bouw. “For new contracts, contractors would be well advised to work with a daily price or a price revision clause to avoid getting into too much difficulty. In the meantime, we are asking the federal government to recognise these circumstances as exceptional.”
A look at construction companies’ order books and liquidity shows that most have regained their momentum. Order books are now filled for an average of 5.9 months. This is the best result since the outbreak of the Covid pandemic. The number of construction companies without liquidity problems is also rising slightly. It seems, then, that the construction sector has quickly weathered the coronavirus crisis.
Unfortunately, the sector is now facing two significant challenges: price rises and supply problems. A survey by the Confederatie Bouw, in which 417 construction companies took part, found the following:
- 57% are facing price rises of 15% or more since the end of last year,
- 29% report price increases of 25% or more,
- 10% even report price rises of 50% or more,
- 4 in 10 expect further price rises of 15% or more over the next 3 months.
For 63% of construction companies, these price rises must be borne entirely by the company under existing contracts.
In addition, 78% of construction companies are currently experiencing supply problems:
- 61% are facing additional delivery times of 2 weeks,
- 31% are even experiencing supply delays of 4 weeks or more,
- 58% also expect additional delivery times of two weeks over the next 3 months,
- 32% expect an additional delay of 4 weeks.
Current supply problems are already causing work delays at 54% of construction companies. In 6% of cases, this has led to postponement by the client, and in 4% of cases to cancellation.
Price rises and supply problems are also having an impact: 8% of construction companies have already had to seek alternative financing, while 15% have had to put staff on temporary unemployment. The Confederatie Bouw therefore recommends using a daily price or a revision clause for unforeseen circumstances in new contracts.
Construction companies also expect the federal government to recognise these circumstances as exceptional. This means that contractors should not have to bear the risks in full, since the price rises are abnormal. The Confederatie Bouw is in talks with the federal government about this.