Contractor breathes a sigh of relief after unprecedented summer

Het viaduct in Gentbrugge werd deze zomer integraal gerenoveerd door Willemen Infra.
Het viaduct in Gentbrugge werd deze zomer integraal gerenoveerd door Willemen Infra.

With a host of major projects on the agenda last summer, the coronavirus crisis could hardly have come at a worse time for Willemen Infra.

The contractor had to pull out all the stops to complete the work on time under these exceptional circumstances. “Thanks to adapted procedures and construction methods, but above all the unprecedented dedication of our people, we managed to complete our summer projects on time,” the company says with justified pride. 

With the renovation of Runway 25R at Brussels Airport (€15.1 million), the renewal of the continuously reinforced concrete (CRC) road surface on the E313 in Beringen (€10.9 million), the replacement of the CRC on the A8 in Halle with new asphalt (€5.4 million), the complete renovation of the viaduct in Gentbrugge, including waterproofing, surfacing, expansion joints, noise barriers, safety barriers and cathodic protection of the concrete (€34.3 million), and the renewal of the central section of Bruges’ Katelijnestraat, including reconstruction of the sewers and natural stone paving (€2.7 million), Willemen Infra has, to put it mildly, had a busy summer. One it hopes never to repeat. “It will come as no surprise that Covid-19 caused considerable disruption,” says Joris De Kesel, regional director for the West Region at Willemen Infra.

In Beringen, Willemen Infra replaced the road surface on the E313.

Projects temporarily halted

On 7 May, Confederatie Bouw, Bouwunie, FeMa and the trade unions ABV, ACV and ACLVB signed a sector protocol setting out several key preventive measures for construction sites. These included maintaining social distance unless absolutely unavoidable, washing hands on arrival, wearing face masks, staying at home if unwell, using individual tools, holding meetings in smaller groups and outdoors, cleaning sanitary facilities more frequently, providing disinfectants, supplying a BPM kit for employees working indoors, and displaying posters to remind everyone of the rules. “When the coronavirus pandemic first broke out, work on our sites came to a temporary halt,” says De Kesel. “But by quickly developing adapted procedures and construction methods in line with the requirements of the sector protocol, we were able to get work under way again. We repeated the need to observe all these measures until we were blue in the face, because we absolutely could not risk an outbreak on site.” 

Particularly proud

This was essential, as Willemen Infra’s summer projects, which continued through the construction holiday, all had tight schedules, meaning short completion periods and changing phases with strict deadlines. “So delays simply weren’t an option,” stresses Marc Verlee, who, like De Kesel, is regional director for the West Region at Willemen Infra. “That’s why we brought in extra staff and equipment. It was a challenge, particularly during the construction holiday, to secure everything we would normally take for granted outside that period. Ensuring the supply of raw materials and coordinating the various schedules were the biggest challenges. Fortunately, we managed it all. We would like to thank everyone involved, especially our own people, whose unprecedented commitment makes us particularly proud.”

Last summer, Willemen Infra renewed Runway 25R at Brussels Airport.

Financial impact

Unfortunately, the coronavirus crisis also had financial consequences for Willemen Infra. Verlee explains: “Alongside the many additional costs, including face masks and extra staff, there were also additional mobility costs because employees had to travel to site on their own. But there is a second, potentially much heavier cost: a huge reduction in the volume of work available on the market. Some forecasts point to a fall of 30%, putting margins under enormous pressure and making the situation untenable for some companies …”

So did Covid-19 have no upsides at all, as strange as that may seem? “I think it is wrong to talk about benefits in the context of this unprecedented crisis,” says De Kesel. “But it is true that for a time our people could get to site and home more easily because there was less traffic congestion, although that has now become a thing of the past. We have also learned some lessons. Online meetings are certainly here to stay, and some adapted construction methods have even proved more efficient,” he concludes.   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.