Seventy-five days. That is how long work came to a standstill at De Watergroep’s Cadol site in Leuven. It was not the result of Covid or exceptional weather conditions, but of the unwelcome discovery that the structure of Block Noord, the building to be renovated, was not sufficiently stable. Thanks to the swift and effective response to this stability issue, including additional structural work, the site was soon back up to full speed. The refurbished building is due for completion in early 2023. 

“While carrying out the demolition work, we had to conclude that the building’s foundations no longer met current standards,” says Simon Reumers.

Work at the Cadol site in Leuven, where De Watergroep produces fresh drinking water, began on 1 October 2021. The brief for main contractor Renotec was clear: install several draw pits and sectional doors, lay new asphalt and, above all, give Block Noord, a former pumping station more than a hundred years old, a fresh new look. “The original plan was for a thorough renovation: strip the building back to its load-bearing structure, reconfigure the layout, completely renew the HVAC and electrical installations … But things took a different turn,” says project manager Simon Reumers.

Ageing foundations 

As no major structural work was initially required, Renotec started with the roofing work. “When we then began the demolition work, mainly removing plaster and taking out plasterboard, we had to conclude that the building’s foundations no longer met current standards. As a result, engineering consultancy Sweco had to carry out a new structural survey. We then sat down with the people from De Watergroep to discuss how we could tackle the problem. In the end, we opted to retain only the external walls and roof, and build an entirely new structure. In terms of stability, we had to start again from scratch.”

Apart from the initial stability issues, the project was particularly challenging from a technical point of view.

A true turnkey project

After work on site had been on hold for 75 days, Renotec resumed work in mid-January 2022. “First, we installed new foundations with micropiles from basement level upwards. We then put in new floors and partition walls, renewed the HVAC systems and sanitary installations, took care of the interior finishes, and carried out the external works, including underground services, new asphalt surfacing, sliding and sectional doors, and so on. In the end, it really did become a true turnkey project,” says Simon Reumers. “We carried out all this work in collaboration with reliable subcontractors, although we were De Watergroep’s main point of contact. Apart from the initial stability issues, the project was particularly challenging from a technical point of view. The site is equipped with an advanced access control and security system, as well as charging points for electric vehicles. So the electrical installations made for a demanding job. We are now on the home straight. We will be able to complete the ‘rebuild and renovation’ in early 2023.”

Work at De Watergroep’s Cadol site in Leuven developed into a true turnkey project.

Expertise and quality

Simon Reumers and his colleagues at Renotec are very positive about the decisive way the unexpected stability issue was tackled. “Sweco discussed every proposal for a new structural concept with us, so that we could make sure everything was technically workable. We were also able to rely on a detailed Revit model during the work, which was continually updated,” explains the project manager. “Relations with the client were excellent too, thanks to weekly site meetings. It certainly helps that we had already carried out several other projects for De Watergroep, including the renovation of Block Oost at the same Cadol site. We are pleased that this project gave us another opportunity to draw on one of Renotec’s major strengths: our flexibility. We have the expertise and specialist skills needed to deliver more challenging or specialised projects successfully. Our interest begins where that of a standard general contractor ends. We also attach great importance to quality. Whether it is a renovation worth a few million euros or the replacement of a door handle, we always apply the same attention to detail and work ethic, whatever the size of the site.”   

Een zakelijke vraag aan Sweco Belgium? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
  • CompanySweco Belgium
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.