High-performance systems for a state-of-the-art logistics hub

The new logistics complex on the western side of Brucargo covers 50,000 m² and is now in the final stages of fit-out. As it is also intended to store temperature-sensitive pharmaceutical products while keeping its environmental footprint to a minimum, high-performance systems are required. These are currently being installed by Cegelec nv (part of VINCI Energies). “The construction period is very short, but for now we are perfectly on schedule,” say project managers Bart Vandermeersch (HVAC package) and Eric Pauwels (electrical package).
The new logistics hub developed by Cargo & Logistics Real Estate at Brucargo, which will be brought into operation later this year by Kuehne+Nagel, Expeditors and WFS, comprises three buildings with offices and warehouses for temporary storage and cargo handling. Working closely with lead contractor Besix and engineering firm Sweco, Cegelec is responsible for installing all the systems: HVAC, electrical, plumbing, rainwater drainage, fire mains, lifts and the sprinkler system. “So this is a single technical package, with Cegelec coordinating all the systems in-house,” explain Bart Vandermeersch and Eric Pauwels. “Combined with the very tight construction period, just one year including engineering, design, work preparation, ordering, installation, start-up and commissioning, this makes completing the project successfully quite a challenge. Fortunately, we have extensive experience with large, complex construction projects, such as those in the pharmaceutical and healthcare sectors, where specific requirements often apply, and state-of-the-art building systems hold no secrets for us. We handle the engineering, programming and testing of the automatic HVAC controls, lighting and building management system entirely in-house. Our sister division VINCI Facilities will monitor and maintain the installations during the warranty period.”

The handling areas in each building are equipped with a sizeable air handling unit (30,000 to 45,000 m³/h) with high-efficiency heat recovery.
A coordination tour de force
Sustainability is one of the key priorities in the construction of this large-scale complex. Solar panels will be installed on the office roofs, and heating and cooling will be provided by air-cooled
four-pipe heat pumps, depending on occupancy levels and orientation. These will supply the radiant ceiling panels in the offices. Rainwater storage and reuse will help keep water consumption down. Energy-efficient LED lighting and charging points for electric vehicles will also contribute, and the ventilation system is environmentally friendly too. “The handling areas in each building are equipped with a sizeable air handling unit (30,000 to 45,000 m³/h) with high-efficiency heat recovery. In total, we are installing 2.5 kilometres of ventilation
ductwork fitted with jets, 20,000 metres of sprinkler pipework with five thousand sprinkler heads, 7 kilometres of rainwater drainage pipes, 5 kilometres of cable trays, gas and fire mains … Coordinating everything properly is a real tour de force. In addition, all the systems have to be installed at a minimum height of 8.5 metres to preserve as much storage space as possible. Even so, we are perfectly on schedule. As we work to detailed weekly plans, we can respond very quickly. Two of the three phases are now complete.”
Een zakelijke vraag aan Sweco Belgium? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectGeneral
- CompanySweco Belgium