High-quality sports facilities with a golden touch

De nieuwe turnhal in Niel is opgebouwd uit een prefabbetonstructuur met voorgespannen IV-liggers, die op punt gesteld is met behulp van een BIM-model.
De nieuwe turnhal in Niel is opgebouwd uit een prefabbetonstructuur met voorgespannen IV-liggers, die op punt gesteld is met behulp van een BIM-model.

The Olympic Games have once again proved that investment in sports infrastructure pays off. Judokas and gymnasts from the area around Niel can now train in a brand-new gymnastics hall with a dojo, where they can look to Olympic gymnastics champion Nina Derwael and fellow local Matthias Casse, who won an impressive bronze medal in Tokyo, for inspiration. In Herent, another Olympic medallist is in the spotlight: the town’s new sports centre has been named after speed skating champion Bart Swings. Two remarkable construction projects designed to inspire ambitious sports enthusiasts to achieve great things …

Bart Swings Sports Centre includes a three-court sports hall of 1700 m² with a combined-elastic sports floor.

Niel’s sports park has recently received a major upgrade. Alongside the youth centre and the existing sports hall, a new gymnastics hall has been built, complete with a dojo and a multipurpose room. The building has a floor area of 900 m², was designed by Studio Klein Brabant and built by Pellikaan. “The new gymnastics hall has a precast concrete structure with prestressed IV beams, designed using a BIM model. The base is made of exposed concrete sandwich panels, while the rest of the façade consists of liner trays with insulation and metal cladding. We also opted for a power-floated concrete floor, which is now fully covered with mats and equipment, and a steel deck with PVC roof membrane and a green roof. Polycarbonate panels in the façades, three in the gymnastics hall and one by the dance studio, provide attractive natural light. We also carried out some renovation work in the existing sports hall, but this was limited to demolishing two existing changing rooms and installing sanitary facilities, two smaller changing rooms and a reception area,” says Lieve De Bleser, project manager at Pellikaan.

Stepping up a gear

The biggest challenge during the work in Niel was an obvious one: the coronavirus crisis. “The lockdown coincided with the first stages of construction, so finding available subcontractors was no easy task,” says Lieve De Bleser. “The ground conditions also caused some problems, and we had to replace part of the planned piled foundations with micropiles. Fortunately, the impact on our schedule was limited, partly because we stepped up a gear in the final stretch. We are very pleased with the result. At first, we were concerned that the black façade cladding would make the building look like a monolithic block, but its carefully designed profile creates an intriguing play of light and a very attractive effect. A great idea from the architects and excellent work by the Pellikaan team!”

A new gymnastics hall with a dojo and a multipurpose room has been built in Niel’s sports park.

A versatile sports centre

Around 40 kilometres further on, in Herent in Flemish Brabant, Pellikaan also made a big impression. Together with Artabel, IRS Studiebureau and studio k, it delivered a prestigious Design & Build project, whose first plans date back to 2016: Bart Swings Sports Centre. The focus was not just on sports facilities, both indoors and outdoors, but also on high-quality landscaping and encouraging social interaction between different types of visitor. Bart Swings, who was born and raised in Herent, had the honour and pleasure of officially opening the complex. The celebrated speed skating champion was clearly impressed by the extensive facilities: a three-court sports hall of 1700 m² with a combined-elastic sports floor and martial arts mats; an 860 m² gymnastics hall with a closed pit system, a full-length tumbling track, unique in the region, a fast track and all the equipment for Olympic gymnastics; two beach volleyball courts; an outdoor fitness area; an asphalt pump track, unique in the region; a skatepark; and a 260 m² brasserie with an outdoor terrace. The site also includes a park area, while a renovated mountain bike route, including a bike wash station, starts at the sports complex. There is also a connection to a Finnish track and an exercise bench. Finally, provision has already been made for the future, with plans in progress to build a swimming pool next to the gymnastics hall.   

The bar was set high for Bart Swings Sports Centre, as the municipality wanted more than just another run-of-the-mill sports hall.

Aesthetics and energy efficiency

Bart Swings Sports Centre uses the same construction approach as the new gymnastics hall in Niel: a precast concrete structure (columns, beams, predalles and hollow-core slabs), a base of concrete sandwich panels, and façades made up of liner trays, insulation and metal cladding. “The bronze colour and folded profile of the façade cladding give the building a distinctive appearance. The aluminium external joinery also fits perfectly, while several polycarbonate panels on the north side provide additional natural light,” says Pellikaan project manager Koen Verhoeven. “The bar was set high, as the municipality wanted more than just another run-of-the-mill sports hall. In many other sports complexes, function takes precedence and aesthetics are neglected, but that is certainly not the case in Herent. The cafeteria, for instance, has a very trendy interior by Studio Boîte, a specialist interior design firm from Leuven, the entrance hall is finished in bamboo, and the liner trays in the sports hall are green rather than the usual white. Another notable feature is that the complex meets the BEN standard. This meant we had to pay very close attention to airtightness. Given the mechanical fixings for the façade cladding, this was by no means straightforward, but our efforts paid off: the airtightness achieved was actually better than specified. There has also been substantial investment in energy performance: thick insulation, solar panels on the gymnastics hall roof, a type D ventilation system …”      

Prepared down to the last detail

The coronavirus crisis initially threw a spanner in the works in Herent too. “Because of the lockdown, work could not really get under way until May 2020, two to three months later than planned. All things considered, though, we could not complain too much about staff absences or delivery problems,” says Koen Verhoeven. “We also used that period of delay to prepare every detail of the work, which certainly helped the project run smoothly thereafter. The sports complex was completed on 20 May this year and officially opened on 21 June. Construction therefore took barely a year, which we can call a success given the circumstances. The landscaping, specifically the planting, will be completed at the end of this year during the planting season. We are very pleased with this fine project. Relations with Herent municipal council were excellent, and cooperation with the other construction partners went very smoothly. The fact that Bart Swings himself was impressed by the result is, of course, the icing on the cake!”

PROJECT PARTNERS SPEAK
GEVITEC: ELECTRICAL INSTALLATIONS AND CABLING
Whether expanding an existing sports hall or delivering a new sports complex on a Design & Build basis, electrical contractor Gevitec (Schoten) is at home in both fields and well equipped to deliver either project successfully. It recently proved this in Niel and Herent, extending its successful partnership with Pellikaan. “We were responsible for the electrical installation, cabling, lighting, access control, connections and power supplies from start to finish,” says Andy Borghs, assistant director at Gevitec. “Our flexibility and proactive approach are key strengths. We can handle not only new installations, but also modifications and extensions. In addition, we can always provide any extras required in consultation with the client. In Niel, for example, we also installed a high-voltage substation, giving the existing sports hall a new power supply too. In Herent, we also took care of the data facilities, sound system and CCTV. The cafeteria fit-out only took shape at a later stage, but that was no problem, as it meant we could make the most of our expertise as part of the overall Design & Build contract. We quickly put the necessary measures in place internally, so we were able to keep working throughout the coronavirus crisis. As a result, the deadlines were not jeopardised, much to Pellikaan’s satisfaction. We work together regularly, so we have an excellent relationship and very direct lines of communication. Here’s to the next one!”

Een zakelijke vraag aan Pellikaan Bouwbedrijf nv? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral