Iconic in every sense of the word

A bold architectural design, a strong identity, creative use of materials, technical innovations … the new BNP Paribas Fortis headquarters makes a striking impression and has won widespread admiration. A landmark building has risen on Warandeberg in the heart of Brussels, immediately catching the eye and meeting every expectation in terms of functionality and environmental performance. It is no surprise, then, that this exceptional construction project has already garnered several major awards …

2013: BNP Paribas Fortis launches a competition to design and build its new Brussels headquarters, replacing two existing towers on an imposing podium above a metro line. 2014: the competition is won by Austrian practice Baumschlager Eberle Architekten, working with Belgian firm styfhals architecten bv nv. 2016: Jaspers-Eyers Architects joins the team to help deliver the project. August 2017: construction gets under way. Mid-November 2021: the imposing office building is provisionally handed over and the bank’s first employees move in. The rest, as they say, is history …

Construction team and dedicated points of contact
The fact that this remarkable feat was completed in record time is largely down to the decision to deliver the project using a construction team approach, and the commitment of all parties involved to appoint two or three dedicated points of contact. Both Christophe Van Ophem (CEO of Eiffage Benelux) and Jenny Scherrer (partner architect at Jaspers-Eyers Architects) praise this carefully considered approach. “The pieces of the puzzle gradually fell into place and, once roles had been assigned, collaboration was excellent,” they explain. “We held meetings with the various partners every week, sometimes even several times a week, specifically to consider how to develop technical solutions for integrating the exoskeleton.”

The exoskeleton gives the new office building its unique identity. Developed early in the process as a load-bearing structure, it reflects the forward-looking design by Baumschlager Eberle Architekten. The exoskeleton comprises 1,280 white architectural concrete elements incorporating specially selected Norwegian aggregates.
Challenges galore
Delivering this striking building posed a host of challenges. So many, in fact, that Jenny Scherrer wondered “whether there was anything routine about this project at all”. The challenges were technical, logistical and architectural, as well as human: at times, up to seven hundred workers were on site at once. In terms of logistics, the building’s location in central Brussels and the limited storage space on site meant that work had to be carried out just in time. Renaud D’Hondt, project director at Valens (Eiffage Group), says: “During both the structural works and the finishing phase, we had twenty to thirty articulated lorries arriving every day, which we had to direct to the right place and unload.”
“We had to put every element straight into its final position to avoid multiplying the number of deliveries and handling operations unnecessarily,” adds Christophe Van Ophem. “This called for extremely strict and precise planning. We are used to managing material flows of this kind on our sites, but obviously not on this scale.” The acoustic requirements, relating to the noise and vibration generated during the works, also had to be strictly observed.
Architecturally, the many curves in the building made the process much more complex, from the initial preparatory stages through to the final finishes. Jenny Scherrer explains: “One of the main difficulties was standardising certain elements in a building full of organic lines. We therefore had to develop production solutions that were optimised both aesthetically and functionally, particularly for the suspended ceilings. The atrium, which spans four levels and features curved volumes, was also highly complex. In addition, the entire structure had to be built with post-tensioned floor slabs of minimal thickness, and the roof’s pronounced slope (nine storeys on one side of the building, six levels on the other) required a very thorough structural stability study.”

Bespoke solutions
Did the teams need to acquire special skills for this highly specific project so they could respond quickly to its many unusual requirements? Renaud D’Hondt says: “We already had most of the necessary expertise in-house, but we had to apply it on a larger scale than usual. The many curved lines in the BNP Paribas Fortis headquarters called for far more preparation and more detailed plans, measurements and adjustments than a conventional building. Working with our subcontractors, for example, we had to develop several new installation systems, including for certain non-load-bearing columns. Other good examples were bespoke suction cups for installing the heavy, imposing curved curtain walls, and drones fitted with fans to position a series of horizontal architectural concrete elements with millimetre precision.”

Pioneering technologies
It is clear that the new BNP Paribas Fortis headquarters is exceptional in many respects. It also stands out for its HVAC systems, thanks to several innovative technologies. “This passive building has achieved BREEAM Excellent certification and uses no fossil fuels, which is rare for an office building of this size (100,000 m²),” explains Christophe Van Ophem. “As well as PV panels on the roof, there is a water reservoir in the basement, roughly the size of four Olympic swimming pools. In winter, four heat pumps extract heat from it, then climate ceilings bring the building up to temperature. In spring and summer, the process is reversed: the water temperature has fallen and is used to cool the building. This is one of the first times that this innovative thermal energy storage system, better known as ‘STES’, has been used in an office building. In this respect too, it is a pioneering project …”

Integration into public space
BNP Paribas Fortis is immensely proud of its new headquarters. That is why it wanted to open certain spaces to the public. Jenny Scherrer says: “Integrating the building into the urban fabric and creating semi-public spaces were key considerations from the outset. The bank did not want a closed-off complex, as had been the case in the past with the massive podium, and wanted public and private space to flow into one another.” Mission accomplished: passers-by can wander freely through the two internal courtyards and discover the building for themselves.
The final word goes to the CEO of Eiffage Benelux: “This project has given everyone involved a great deal of satisfaction, both the people behind the scenes, namely the project engineers, modellers and BIM managers, and the site teams. Everyone was able to use their imagination to develop the best solutions and deliver the building on time and to a high standard. The new BNP Paribas Fortis headquarters is emblematic for four key reasons: its scale, its bold and ambitious architecture, the quality of its interior and exterior finishes, and its location. You do not come across an exceptional project like this twice in your career.”

Question about this story? Ask your question
Wie aan Hoofdkantoor BNP Paribas Fortis werkte
- main contractorCIT BlatonMentioned in High-performance coating protects striking headquarters from moisture and pollution
- prefabbetonleverancierLoveldMentioned in High-performance coating protects striking headquarters from moisture and pollution
- architectsBaumschlager EberleMentioned in High-performance coating protects striking headquarters from moisture and pollution
- architectsStyfhals & PartnersMentioned in High-performance coating protects striking headquarters from moisture and pollution
- architectsJaspers-Eyers ArchitectsMentioned in High-performance coating protects striking headquarters from moisture and pollution
- beschermende coatingsAPP All RemoveMentioned in High-performance coatings preserve iconic headquarters
- architectBaumschlager Eberle ArchitektenIn this story
- architectstyfhals architecten bv nvIn this story
- main contractorEiffage BeneluxIn this story
- clientBESIXIn this story
- painting worksSilocIn this story
- construction companyEiffageMentioned in BNP Paribas Fortis headquarters wins top honour at MIPIM in Cannes
- producent en plaatserMetosMentioned in Almost 100 years of experience as a one-stop solution for professional kitchens
- levering van het glasAGCMentioned in BNP Paribas Fortis head office, Brussels: Creative use of glass
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBNP Paribas Fortis headquarters
- SubjectGeneral
- CompanyBaumschlager Eberle Architekten
- Companystyfhals architecten bv nv
- CompanyEiffage Benelux
- CompanyBESIX
- CompanySiloc