The Spa-Francorchamps circuit has been a fixture on the Formula 1 calendar for years. The Belgian Grand Prix is also on the F1 calendar in 2023. Thanks to a new grandstand at the famous Raidillon corner, spectators can once again enjoy the roar of engines and the screech of tyres to the full.
On Sunday 28 August, the Formula 1 circus rolled into Spa-Francorchamps for the Belgian Grand Prix. Tens of thousands of motorsport fans made their way to Wallonia, flags flying, and found plenty to cheer about. No wonder: in the months beforehand, a great deal of work had gone into getting the circuit back into top condition. To meet the strictest safety standards, obtain the necessary FIA homologations for motor racing and once again allow endurance races for motorcycles, the circuit underwent a thorough overhaul. The surrounding infrastructure was also upgraded to give the many spectators an even better viewing experience. The first phase saw the construction of a new grandstand with 4,600 seats and a magnificent view of the steep Raidillon. This winter, a new 24-hour race grandstand will also be built, replacing the familiar endurance grandstand towards Eau Rouge.

A job for a steel construction specialist
Commissioned by TV Francorchamps-MOTO 22, the temporary partnership between Wust and Serbi, ASK Romein gave the Spa-Francorchamps circuit a new look during the winter break. “We were brought in as steel construction specialists to build the steel canopies above the grandstands and install the steel deck roof sheets,” says Technical Director Luc Moonen. “The grandstands’ substructure consists of a prefabricated concrete structure. The canopy is supported by the rear column and comprises a column and a beam in the form of a box section with a variable depth. This box section is made from plates welded together. Behind the grandstand, a tie connected to a heavy foundation block counterbalances the cantilevered beam. The canopy above the Raidillon grandstand weighs around 230 tonnes and cantilevers 22 metres from the column. The canopy above the 24-hour race grandstand will weigh around 208 tonnes and cantilever 24.5 metres.”
Tight deadline
“Without doubt, the biggest challenge in building the Raidillon grandstand was the schedule,” stresses Luc Moonen. “The preparation period was short, leaving us just over two months to order the materials and manufacture the steel structure. Production preparations began in early December 2021. We started assembling and welding the beams in mid-December, and delivered the first beams on 14 February 2022. The canopy structure and steel deck had to be installed in just three and a half weeks. No easy task, particularly as we faced stormy weather right from the first week. Nevertheless, we completed the final finishing work on 8 March and handed over the structure to the main contractor on schedule. Roadworks and other work were also taking place while the steel structure was being installed. It was therefore decided to use a heavier 500-tonne crane, which could be positioned further away from the grandstand. We also had to provide several working platforms so that the cranes and access platforms could operate properly on the steep slopes of the Raidillon. Building and removing these platforms inevitably involved extra work.”

Galvanising and corrosion protection
Finishing the steel also proved a challenge. “The original plan was to galvanise the entire structure, but as the main beams are box sections made from relatively thin plate, the risk of distortion during galvanising was too high. We therefore opted to protect the trusses with a three-coat paint system, while the other parts of the structure were hot-dip galvanised. Given the size of the beams, we manufactured and protected them at our facility in Katwijk (NL). Including the welded-on column, they could be shot-blasted and protected as complete units there, avoiding the need for joints in the beam and eliminating the risk of moisture ingress,” explains Luc Moonen. “We are very pleased with the result. Despite the tight schedule and difficult weather conditions, we installed an impressive steel structure fully in accordance with the agreed arrangements. The Raidillon grandstand’s iconic location in the world of motor racing adds to the prestige of this project.”
Question about this story? Ask your question
Who worked on it
Raidillon-tribune in Spa
- clientLe Circuit de Spa-Francorchamps
- architectLuc Nelles Architectes Associés
- engineering consultancyBureau d'études JML Lacasse Montfort
- main contractorTV Francorchamps-MOTO 22
- luifels en dakplatenASK Romein
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRaidillon-tribune
- SubjectGeneral
- CompanyLe Circuit de Spa-Francorchamps
- CompanyLuc Nelles Architectes Associés
- CompanyBureau d'études JML Lacasse Montfort
- CompanyTV Francorchamps-MOTO 22
- CompanyASK Romein