General

Not a drop of dewatering water wasted

De grondwaterstand (en afregeling) van de installatie werden vanop afstand gemonitord aan de hand van sensoren.
De grondwaterstand (en afregeling) van de installatie werden vanop afstand gemonitord aan de hand van sensoren.

Building the new Krokodiel public swimming pool in Middelkerke required a large excavation.

Given the site’s specific location, obtaining a dewatering permit was no easy task. Nevertheless, G. Smeyers managed to devise a solution that won approval from all the authorities involved. All the water pumped out was reinfiltrated into the ground, a welcome measure in these times of drought!

Building the new leisure pool required an excavation measuring approximately 100 x 40 metres. It had to be dug from the existing ground level of +4.50 TAW down to +1.00 TAW. “Technically, bridging a difference of 3.5 metres is not particularly difficult,” says René Lambrechts, director of G. Smeyers. “The challenge was the location: this new attraction in Middelkerke is right next to a protected dune area. Any adverse impact on groundwater levels could have serious consequences for local flora and fauna. It is no surprise, then, that the relevant authorities, particularly the Vlaamse Milieumaatschappij and Agentschap Natuur en Bos, attached very strict conditions to the dewatering permit. In other words, this was a case that required specialist expertise. That is why main contractor Cordeel once again decided to call on our expertise.”

The dewatering system was designed using a 3D computer simulation model and installed with horizontal drains.

After thoroughly studying the available ground investigation data, G. Smeyers proposed carrying out the dewatering within a groundwater cut-off wall extending down to -10.00 TAW. “The dewatering system was designed using our own 3D computer simulation model, and horizontal drains were specified for its installation,” says René Lambrechts. “The impact of dewatering outside the excavation was offset, first, by a series of infiltration filters at the foot of the dune area. The
remaining pumped dewatering water was reinfiltrated through an infiltration field with horizontal drains. The excavation has now been dewatered to the required depth. And we are particularly proud to say that 100 % of the pumped dewatering water was successfully reinfiltrated.”   

TECHNICAL DETAILS

Client Gemeente Middelkerke
Architect Slangen en Koenis Architecten (IJselstijn, Nederland)
Main contractor(s) Cordeel (Temse)

Een zakelijke vraag aan G. Smeyers N.V? Get in touch

Wie aan Krokodiel werkte

  1. main contractorCordeelMentioned in Krokodiel private swimming pool, Middelkerke | Not a drop of dewatering water wasted
  2. ClientGemeente MiddelkerkeIn this story
  3. ArchitectSlangen en Koenis ArchitectenIn this story
  4. main contractorVita GroepMentioned in State-of-the-art sports complex blends into the dune landscape
  5. architectSlangen+Koenis ArchitectenMentioned in State-of-the-art sports complex blends into the dune landscape
  6. zwembadspecialistHellebrekersMentioned in State-of-the-art sports complex blends into the dune landscape
  7. operatorFarysMentioned in State-of-the-art sports complex blends into the dune landscape
  8. keerwandenCBS BetonMentioned in State-of-the-art sports complex blends into the dune landscape

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectKrokodiel
  • SubjectGeneral
  • CompanyGemeente Middelkerke
  • CompanySlangen en Koenis Architecten
  • CompanyG. Smeyers N.V
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.