A new five-storey park-and-ride facility was inaugurated in Anderlecht on 19 May, the first in a whole series of multimodal hubs intended to help ease congestion in the capital. The new car park accommodates 1,200 cars, 150 motorbikes or shared cars and 270 bicycles. Its prime location alongside the western ring road, and its visibility from it, make the new P+R very easy to reach. Its immediate proximity to CERIA metro station, a cycle route, two higher education campuses and large commercial sites is another major asset.

The expanded-metal façade enhances the P+R’s welcoming image, giving it a bright and attractive appearance.
P+R Ceria: Coovi has a total floor area of 30,000 m² and was delivered under a Design-Build-Finance contract for Brussel Mobiliteit, awarded to Willemen Groep in 2016. Willemen acted as the client and assembled a project team comprising architects DDS+, Franki (main contractor), Arcadis (structural and building services engineering) and Avantgarden (landscape design). Frédérique Mawet, Project Manager at Arcadis: “We really worked as a team. The main challenge was not just the budget, but also the functionality of the car park.”
A site with distinctive characteristics
The site has several distinctive characteristics that had a bearing on the project, particularly on structural stability. The sloping terrain, for example, meant the car park had to rise gradually, as it was impossible to build part of it below ground without losing its classification as an ‘open car park’. Since the partially cantilevered access ramp is lower than the junction between the adjoining road and the ring road, specific reinforcement and earthworks were required on that side. In addition, the building is supported on piles because of the limited bearing capacity of the ground. Finally, during the earthworks, precautions were taken to avoid clashes with a nearby Fluxys gas pipeline, particularly around the embankment and retaining wall between the Brico store and the car park building.

The design is based on the diagonal, with V-shaped columns on the lower levels breaking up the typical verticality of buildings of this kind. The diagonal lines continue on the upper floors.
The above-ground car park was handed over as a shell, including the façade, structure and floor markings. The remaining equipment, including the space-counting system, access control and signage, as well as the operation of the facility, were covered by a separate tender.
A visually striking composition
Where the entire plot was once occupied by an open-air car park belonging to the Brussels-Capital Region, a visually striking development with a small footprint now stands. Didier Peremans, project architect at DDS+: “We wanted to give the car park an attractive character. It certainly wasn’t going to be a conventional ‘box’. The design is based on the diagonal, with V-shaped columns on the lower levels breaking up the typical verticality of buildings of this kind. The diagonal lines continue on the upper floors, thanks to an expanded-metal façade that enhances the P+R’s welcoming image.” Using two metal meshes creates a play of light and reflection, giving the whole development an aesthetic dimension. The distinctive use of colour inside makes the different floors easy to identify intuitively, allowing the signage to be kept simple.
Didier Peremans: “We organised a project visit for the DDS+ team. Everyone was surprised by the brightness, the natural light and the car park’s pleasant look and feel. Inside, it is striking how few columns there are, creating a remarkably spacious feel. At night, the façade lighting also makes the car park more visible.”
Safe and functional
The expanded metal also serves a functional purpose: it allows natural ventilation while acting as a balustrade and an anti-intrusion barrier. “The façade had to be relatively closed to give the impression of being inside a building, but at the same time it needed to be sufficiently ‘permeable’ to provide a degree of natural ventilation that meets fire brigade standards. As the building is slightly more than 60 metres wide, a regulatory exemption was nevertheless needed to avoid installing sprinkler and smoke and heat extraction systems.”

The distinctive use of colour inside makes the different floors easy to identify intuitively.
The project’s strength lies in the clear layout, which makes the building suitable for all users. It prevents conflicts between different user flows and optimises circulation within the car park. A clear distinction has been made between the zone for private cars on the upper floors and the multimodal zone on the ground floor, intended for motorbikes,
bicycles and cars used in alternative and/or sustainable ways, such as carpooling, car sharing and electric vehicles. To make the car park user-friendly for everyone, considerable attention has been paid to accessibility for people with reduced mobility. Not only is the area for cars secured, but half of the bicycle parking spaces are too, through fencing with access control.
Welcoming and sustainable
The building’s small footprint made it possible to improve the permeability of the
ground and reduce its visual impact from Bergensesteenweg. The remaining
open space has been landscaped as a green area. The space between the car park and the metro is free of motorised traffic and serves as a square for pedestrians and cyclists. It can accommodate one or two small businesses, such as a bookshop or a bicycle hub, catering to commuters, to create a welcoming atmosphere and a degree of natural surveillance.
Vegetation has not been overlooked. A new green embankment acts as a noise barrier, limiting noise from the ring road. Trees and plants enhance the site and help purify the air. Most rainwater infiltrates directly into the site thanks to a swale. The roofs have not been planted, keeping open the option of extending the building upwards, including the installation of photovoltaic panels or small wind turbines.
Question about this story? Ask your question
Who worked on it
P+R Ceria – Coovi in Anderlecht
- clientWillemen Groep
- architectsDDS+
- main contractorFranki
- structural and building services engineering consultancyArcadis
- omgevingsinrichtingAvantgarden
Keep following this
Get an email when a new story is published. No account needed.
- ProjectP+R Ceria – Coovi
- SubjectGeneral
- CompanyWillemen Groep
- CompanyDDS+
- CompanyFranki
- CompanyArcadis
- CompanyAvantgarden