Rain delays cause financial difficulties for 2 in 3 construction and installation companies

At last, summer is making a tentative appearance in our country. The poor weather over the past 8 months has left 9 in 10 construction and installation companies carrying out outdoor work behind schedule, with delays in many cases now stretching to 1 to 3 months. To catch up, 4 in 10 construction companies will have their employees work more overtime than usual in the coming weeks. The construction holiday will, unsurprisingly, remain largely untouched: 83% will not change it. Those that do will move it by only a few days to a week. This is possible, of course, provided employees agree. Rain-related delays are reducing construction companies’ income, while their fixed costs continue to mount. As a result, two-thirds of construction and installation companies are facing financial difficulties because of the wet weather. “As during the Covid pandemic, we are therefore calling for a deferral of VAT and social security contributions,” says Niko Demeester, CEO of Embuild.
It may finally be starting to feel a little like summer, but according to the KMI, there has never been as much rainfall since records began as there was between October 2023 and May 2024. And during the first three weeks of June, the rain continued to pour down. This record rainfall has also caused problems for the construction and installation sector: no fewer than 89% of companies carrying out outdoor work are currently behind schedule. Half of construction companies have delays of as much as 1 to 3 months, while 12% are more than 3 months behind.
Niko Demeester, CEO of Embuild: “Fortunately, 68% of clients now understand these delays, and they can be confident that our companies will catch up as quickly as possible. Given the substantial delays, it will be impossible to clear the backlog completely before the construction holiday. We will also have to step up our efforts after the construction holiday to gradually catch up.” In the coming weeks, 39% of construction and installation companies will have their employees work more overtime than usual to tackle these delays.
The construction holiday, which starts in most provinces in the second week of July, is unlikely to be changed to address the backlog. A total of 83% of construction and installation companies will keep to the construction holiday as previously agreed, despite the considerable delays caused by the record rainfall in recent months. “That makes sense, because construction workers and company directors have already agreed their holiday plans with each other well in advance. In practice, it will be very rare for those plans to change now. After all, our construction workers are entitled to a holiday too,” says Niko Demeester, managing director of Embuild. Companies that do adjust the construction holiday will make only minor changes, moving a few days or up to a week of holiday.
The exceptionally wet weather has also had financial repercussions: 66% of construction and installation companies are experiencing financial difficulties as a result, with 4% facing very serious difficulties. Fixed costs continue to accrue while income dries up, putting increasing pressure on construction companies’ cash flow. Embuild is therefore calling for a deferral of VAT and social security contributions, as was the case during the Covid pandemic. The construction federation also says that any penalties for late completion would be inappropriate at this time.