Rebuild Belgium: we face the biggest construction and renovation challenge since the Second World War
Text and images Embuild Tekst

Belgium is on the brink of an unprecedented construction and renovation boom. Not only is its housing stock ageing, but public buildings and infrastructure also need a thorough overhaul. What is more, population growth will put additional pressure on the existing building stock in the decades ahead. “The construction and building services sector has a key role to play in renewing the country, on a scale not seen since the post-war reconstruction after the Second World War,” stresses Niko Demeester, CEO of Embuild.
Our country currently has 5.7 million homes. They are 75 years old on average, and 92% do not meet the 2050 energy standards. In concrete terms, this means that 5.2 million homes need to be renovated. The current pace of renovation is far too slow, however: only 0.8% of homes are renovated each year (40,000 homes), whereas at least 4% would need to be renovated to meet the 2050 targets (205,000 homes). At present, 112 homes are renovated each day in our country, but we need 574 renovations a day. The pace therefore needs to increase fivefold.
In addition, 900,000 extra homes will be needed by 2050 as a result of population growth (+800,000 residents), changing housing needs (more single people, single-parent families and older people living independently for longer) and a sustained increase in demand for second homes.
Public buildings are ageing too
This much-needed wave of renewal is not limited to private homes. Schools, hospitals, residential care centres and prisons, among others, also need a thorough modernisation. These buildings are 50 years old on average, and 95% of them need renovation.
6,767 of Belgium’s 7,123 school buildings need to be renewed. What is striking, however, is that no additional schools will be needed by 2050. The reason is demographic: the number of young people aged 3 to 25 will fall by 2%, or 56,000, between now and 2050.
1,447 of the 1,523 residential care centres need work. By 2050, up to 486 additional residential care centres will also be needed as a result of an ageing population. In addition, 98 of Belgium’s 103 hospitals do not meet energy standards. A further seven hospitals will be needed because of the ageing population.
Finally, 37 of the 39 prisons need to be renovated. Growth in the adult population and overcrowding in existing prisons mean that nine additional prisons will also be needed.

Renewing roads, bridges and tunnels
The road infrastructure is also in need of renewal. Our country has 15,032 kilometres of motorways and regional roads. Of these, 18% need to be completely replaced (2,725 kilometres) and 15% thoroughly renovated (2,234 kilometres). Of the 9,206 bridges and tunnels on motorways and regional roads, 3% need replacing (309 bridges and tunnels), while 4% require structural work (365 bridges and tunnels). In addition, many local roads, cycle paths, pavements, railways, waterways and utility networks also need to be modernised and expanded.
Niko Demeester, managing director of Embuild: “The figures are clear. Belgium faces an immense renewal of its homes, buildings and infrastructure. To meet climate targets and respond to demographic change, we need to build and renovate on a massive scale. This is a challenge, but also an opportunity to improve our society and economy. With the right policies and sufficient investment, we can prepare our society for the future.”