Sophisticated foundation techniques for the prestigious Ensor Towers

Striking architecture, breathtaking views, an exceptionally high standard of finish …: the Ensor Towers will literally and figuratively become Oostend’s new high point.
As two iconic landmarks on the prestigious Oosteroever, they will give this long-awaited ‘neighbourhood by the water’ a metropolitan feel. However, building the soaring towers required an ingenious combination of foundation solutions. This was right up the street of Lameire Future Foundation Technics, part of the 2Fund group, which was able to use almost all its tried-and-tested techniques and demonstrate its extensive expertise.

‘Perfection emerges when light and colour blend together,’ the Oostend-born art icon James Ensor once said. This is the guiding principle behind the Ensor Towers, which will house 109 and 97 apartments respectively. Like the paintings of the British-Belgian master, the towers boast a distinctive aesthetic that fits perfectly with Versluys Groep’s other stylish developments on the attractive Oosteroever. The Ensor Towers will leave an indelible mark on Oostend’s skyline, while residents will enjoy splendid views of the sea, the coastline, the city centre, the hinterland, the harbour and/or the new Ensor Park. Large windows, generous living-outdoor terraces and a carefully considered layout guarantee exceptional living comfort. With different finish levels and interior options to choose from, residents can fully personalise their apartment or penthouse. It is clear that, together with neighbouring developments such as Baelskaai 12, the Ensor Towers are the new landmarks of the Belgian coast.
A combination of techniques
The first Ensor Tower is now almost complete, but the second is yet to be built. Last spring, Lameire Future Foundation Technics carried out the complex foundation works. “Given that many other buildings have already been erected on Oosteroever and the walls will be subjected to different loads, we had to use a wide variety of foundation techniques,” explains managing director Yves Lameire. “The inside of the tower will rest on 98 cased bored piles, 52 cm in diameter and 21.5 metres deep, with a secant pile wall defining its perimeter. To support the basement excavations, we installed 100 linear metres of secant piles, 52 cm in diameter and 21 metres deep, 140 linear metres of CSM walls, 17 and 21 metres deep, and a temporary 29-metre sheet pile wall (AZ 18). The temporary sheet pile wall was needed to allow deliveries to the first tower and the other nearby buildings, since the entire site area has been excavated, leaving no room to store materials and machinery. We always plan a step ahead with future phases in mind. Finally, we drilled 99 micropiles (30 T) at the bottom of the excavation, which act as tension anchors.”

A Herculean feat during lockdown
“The depth was the main challenge, since 21 metres is close to the maximum capacity of our largest machine,” says Yves Lameire. “We have a very good relationship with Groep Versluys, have carried out many other foundation works on Oosteroever and are one of the few specialists with the necessary equipment and expertise to handle such varied assignments, so we were the right people for this particular job. The deadline was very tight, so the different foundation techniques had to be carried out simultaneously. It was a Herculean feat of logistical planning and coordination, especially as we carried out the work during lockdown and therefore had to comply with additional health and safety measures. Fortunately, this is one of our strengths, and everything went smoothly!”
Een zakelijke vraag aan Lameire Funderingstechnieken? Get in touch
Wie aan Ensor Towers werkte
- property developerVersluys GroepMentioned in Twin hoists help keep construction time for Ensor Towers in check
Keep following this
Get an email when a new story is published. No account needed.
- ProjectEnsor Towers
- SubjectGeneral
- CompanyLameire Funderingstechnieken