Tailor-made solutions of the purest kind
Text and images Deschacht

Over the past few months, Aclagro built a small-scale wastewater treatment plant (KWZI) on the Klijtebeek in Heuvelland, West Flanders, on behalf of Aquafin. The contractor worked with experts from Collinet on the project. Patricia Bauwens, Head of the Business Office at Aclagro, explains how the collaboration worked in practice.
“This KWZI project supports the local authority’s and Aquafin’s aim of improving the water quality of the Klijtebeek,” Patricia Bauwens confirms. “To ensure the treatment plant operates optimally, the Flemish Environment Agency instructed the municipality of Heuvelland to disconnect as much rainwater as possible from the sewer pipes in the village centre and discharge it locally into the Klijtebeek. The construction of a separate sewer system was also part of the plan.”

Six HDPE manholes
To prepare and develop the project, Patricia Bauwens and her colleagues drew on Collinet’s expertise. “Their team produced the construction drawings and manufactured six HDPE manholes, three of them made from double-wall pipes with a diameter of 1,500 millimetres. We also relied on Collinet to install the overflow penstocks and wall-mounted penstocks in the manholes, and to fit glass-fibre-reinforced gratings on them, including the necessary supports.”
Plug and play
Kristel Vanmolle, Sales Engineer at Collinet, explains the advantages of the manholes. “One of their strengths is that a range of accessories, such as wall-mounted penstocks, overflow penstocks and valves, can easily be installed in them. These can be operated either manually or electrically. They are also easy to access for maintenance and inspection. As the supplier, we were also able to prepare the manholes in our workshop and deliver them to site ready to install. Their lightweight HDPE construction enabled us to guarantee rapid installation in collaboration with Aclagro.”

Overflow penstocks and wall-mounted penstocks
Both the overflow penstocks and the wall-mounted penstocks will soon prove useful, Patricia Bauwens confirms: “The overflow penstocks are designed to maintain the upstream water level. The customer can set the required level with a simple turn, with excess water flowing over the penstock plate to the lower-lying property. Wall-mounted penstocks are used to temporarily block or allow the passage of (waste)water.”
Deadline met
“The manholes were completed on site at the end of June 2023, with GRP gratings fitted on top,” says Kristel Vanmolle. “The planned handover deadline, before the 2023 summer construction holiday, was therefore easily met. This was partly thanks to the excellent collaboration between the Collinet and Aclagro teams!”
Een zakelijke vraag aan Deschacht? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectGeneral
- CompanyDeschacht