Article 1794 of the Civil Code states: “The client may terminate a fixed-price contract at their sole discretion, even if the work has already begun, provided they compensate the contractor for all their expenses, all their labour and everything they could have earned from the contract.” This provision is one of the cases in which the law allows a contract to be brought to an early end, even though, in principle, contracts are binding on the parties (see Article 1134, second paragraph, of the Civil Code).
This right of termination belongs solely to the client, and, by extension, to the receiver of a bankrupt client, and, in the case of subcontracting, to the main contractor. The provision is based on the assumption that construction work often takes a long time, and that, as time goes by, it may no longer be necessary or useful to the client, or may exceed their financial means. In such cases, it is advisable to give the client the option of terminating the contract.

Unlike termination for breach of contract, Article 1794 of the Civil Code is not based on any notion of fault and does not require a court ruling. Termination under this provision also has effect only for the future, whereas termination for breach of contract is, in principle, retroactive. Compensation is also limited to the items listed in the law.
It is worth noting that Article 1794 of the Civil Code applies to all construction contracts, whether for physical or intellectual work, and therefore also applies to contracts with architects and members of other liberal professions.
To exercise the right to terminate, the client need only notify the contractor, with no formal requirements. This can be done expressly or implicitly. No reason for termination need be given, and the client does not have to offer to pay the compensation specified in Article 1794 of the Civil Code. Nor is prior formal notice of default to the contractor required. The contract may be terminated at any time, both before the work begins and while it is under way, in respect of all or part of the work to be carried out.
To be continued in the next issue of Bouwen aan Vlaanderen (3).

Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectGeneral