The right to compensation when the client terminates the contract for work
Text Antoine Degryse (Belexa)Image Belexa

Under contracts for work, Article 1794 of the former Civil Code (OBW) gives the client the right to terminate the contract at any time by their unilateral decision. Such termination is therefore not ‘wrongful’, although the client must compensate the contractor for their expenses, work and loss of profit. But what is the best way to deal with this in practice?
If nothing has been provided for in the contract, the contractor must rely on Article 1794 OBW and provide evidence of their expenses, work and loss of profit, which will not always be straightforward. This requires the relevant (accounting) documents to be carefully examined by both the client and the court.
Since compensation for expenses, work and loss of profit can also be agreed by the parties in advance as a lump sum, many contractors include the necessary provisions in their general terms and conditions to avoid the cumbersome process of presenting evidence. This also gives the client a clearer idea in advance of where they stand. A win-win situation, then? Yes, but once again, be careful when dealing with clients who are consumers.
In a judgment dated 5 May 2023, the East Flanders Court of First Instance, Dendermonde division, limited this lump-sum assessment in relation to consumers. The provision in question read: “Any cancellation of a contract that has been concluded shall give rise to lump-sum compensation of 30 % of the total
contract price.”
Applying the definition of an unfair term (Art. I.8, 22° Code of Economic Law), the court held that there was a manifest imbalance between the rights and obligations of the parties, to the detriment of the consumer. The term in the general terms and conditions was deemed ‘non-reciprocal’, and the termination fee was ‘manifestly excessive in the circumstances’. The ‘circumstances’ in question were that the contractor had so far only prepared quotations and made one site visit, while the work had not yet started and no materials had been ordered.
This interpretation is open to criticism. First, in our view, the clause in the general terms and conditions providing for a termination fee is indeed reciprocal. It states that ‘any cancellation’ of a contract that has been concluded gives rise to lump-sum compensation. In other words, this also applies if the contractor is the one who cancels.
One might also ask whether compensation of ‘30 % of the contract price’ is manifestly excessive by definition simply because only limited work has been carried out. The specific test that should have been applied was whether the compensation was manifestly excessive in relation to the loss of profit. It is therefore advisable not simply to set this lump-sum compensation at 30 %, but to take account of the three elements: ‘expenses, work and loss of profit’.
The court also held that it could not reduce the unfair term by reverting to Article 1794 OBW, in view of the case law of the Court of Justice.
When drafting such a clause, we therefore consider it useful to be somewhat more comprehensive and to provide for various scenarios based on who terminates the contract and when, while ideally making a clear reference to Article 1794 OBW and setting out an assessment based on the three elements in Article 1794 OBW. The alternative is to make no provision and rely on the general law, resulting in cumbersome proceedings. In our view, this benefits no one.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectGeneral