Three-quarters of construction companies are behind schedule due to heavy rain since October 2023

It has rained an enormous amount over the past six months. The period from October 2023 to March 2024 has broken almost all rainfall records: according to the KMI, this level of precipitation occurs only once every 50 years. It is therefore hardly surprising that no fewer than 74% of construction and installation companies have fallen behind schedule in recent months as a result of the heavy rain. On average, they are 2 to 4 weeks behind. For 30% of companies, however, the delay has stretched to more than 4 weeks. “This is clearly a case of force majeure, and there is little that can be done about it, especially given the historically high rainfall. We therefore ask our customers for understanding,” says Niko Demeester, managing director of construction federation Embuild.
It is raining frequently again this week. This has been the case almost continuously since October 2023. According to the KMI, such conditions are highly unusual, occurring only once every 50 years. They are having a negative impact on construction activity: in persistently wet weather, bricks do not bond as well during bricklaying, and the work takes much longer to dry. In recent months, it has also sometimes been impossible to keep excavations dry, even though they are needed to lay a site’s foundations. In addition, building sites become less safe and much harder for workers and all kinds of machinery to access, partly because of muddy tracks caused by the heavy rain.
Overall, 74% of construction and installation companies have fallen behind schedule as a result of the heavy rainfall, according to a survey by Embuild involving 203 construction and installation companies. Only 18% experienced no disruption from the rain, as their work takes place almost entirely indoors. In other words, virtually all construction companies carrying out outdoor work have been affected, with many experiencing significant disruption during the prolonged spell of rain.
· 6.6% are less than 1 week behind schedule
· 10.5% are 1 to 2 weeks behind schedule
· 25.7% are 2 to 3 weeks behind schedule
· 27.6% are 3 to 4 weeks behind schedule
· 29.6% are more than 4 weeks behind schedule
Niko Demeester, CEO of Embuild: “Unfortunately, only half of our customers show any understanding of the delays affecting construction sites. We understand that this is not ideal for them, but hopefully they will realise that this really is a case of force majeure. Customers can also be confident that construction companies will make up for these delays as quickly as possible once the weather improves.” 30% of construction companies are trying to make up lost time by bringing in additional subcontractors, while 14% are doing so by working extra overtime. 7% are temporarily refusing to take on new contracts.
The same survey by Embuild found that:
· 2.6% of customers are very understanding about these delays
· 12.5% are very understanding
· 45.4% are moderately understanding
· 28.9% are not very understanding
· 10.5% are not understanding at all
Question about this story? Ask your question