Tracking demolition waste mandatory for larger demolition projects

Tracking demolition waste mandatory for larger demolition projects

From summer 2022, waste tracking will be mandatory for larger demolition, renovation and decommissioning projects. Tracimat can help you with this tracking. A demolition waste management plan has already been mandatory for larger projects for some time. But from 1 July, tracking will also be a mandatory requirement for larger demolition, renovation or decommissioning projects for which an environmental permit is applied for.

When is a demolition waste management plan mandatory? A demolition waste management plan lists all the waste materials that will be generated during demolition. It must be drawn up for demolition, renovation or decommissioning projects involving

  • non-residential buildings with a building volume of more than 1,000 cubic metres;
  • predominantly residential buildings with a building volume of more than 5,000 cubic metres, excluding single-family homes;
  • infrastructure works and infrastructure maintenance works with a rubble volume of more than 250 cubic metres. 

Under the new regulations, tracking will be mandatory from 1 July 2022 whenever a demolition waste management plan is required.

Find out more

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectGeneral
Share this article

Follow Bouwen aan Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.