Lier beguinage prepares to welcome new residents
Text and images Koen Mortelmans

The second of five restoration phases is in full swing at Lier beguinage. The works involve twelve houses, which will be made available for residential use once the work is complete, in mid-2026. As heritage buildings recognised by UNESCO, they will not be sold, only let.
With 95 houses spread across eleven streets, Lier beguinage is a typical example of a street-type beguinage. It was established in the thirteenth century, although most of the houses date from several centuries later. Today’s beguinage is a miniature town of around 2 hectares, enclosed by brick walls. Each house is named after a saint or a symbol. The homes are built in a predominantly restrained, heterogeneous brick style, with occasional use of sandstone. Most are wide or deep houses, with one or two storeys, round-arched doorways and front gardens. Numerous alterations, particularly during the nineteenth century, make it difficult to establish their original condition.

Family homes and B&B
Contractor PIT-EIFFAGE is converting five béguine houses on Hellestraat and six on Sint-Margaretastraat into family homes with two to four bedrooms, to designs by Architecten Beeck & Hermans. A twelfth house, at Martienushoek, is being repurposed as a B&B. It will not open until the public realm works have also been completed.
The workshop on Hellestraat is being upgraded and incorporated into the visitor route from Begga’s hof, the central meeting point, allowing it to be given a new multifunctional use. The homes’ new tenants will be able to use a separate covered cycle parking area on Hellestraat. Visitors arriving by bicycle must park outside the beguinage. “The existing garden wall on this undeveloped plot is also part of the restoration works,” says project manager Raf Vandeweyer of PIT-EIFFAGE. “Walls like these also have heritage value.”


“Most of the houses in this phase date back to the seventeenth and eighteenth centuries,” says Fien De Laet of Architecten Beeck & Hermans. “Only Martienushoek and one building on Sint-Margaretastraat were built in the nineteenth century, after an older building had been demolished.”
St-Pieter, at Martienushoek 2, is the largest house in this restoration phase. “Several plots were combined when it was built to create a more spacious property. Thanks to its many large rooms, broad staircase and large garden, the house is well suited to conversion into a B&B. “The first floor will have three guest rooms with adjoining bathrooms. All valuable interior features, such as the plaster ceilings, the half-landing staircase, the panelling and the doors, will be retained.” PIT-EIFFAGE will soon also restore the adjacent Piepenholleke, the premises of the local guild Heren van Lier. “Until a few years ago, all the houses were occupied,” explains Raf Vandeweyer. “Most were no longer suitable as homes because of their physical condition and lack of comfort.”
A blend of old and new
“After inspecting the foundations and masonry, we replaced the damaged sections of the façades,” Raf Vandeweyer continues. “Sometimes this involved just a single brick, while in other cases we had to replace substantial areas. We salvaged all the reusable local bricks and supplemented them with similar bricks from demolition projects elsewhere. We removed the cement render and rebuilt the masonry using lime mortar. The interior walls were also injected to prevent rising damp.”
“We demolished the entire interior and all the outbuildings in each house. We carefully removed the roof tiles so that as many as possible could be reused. We also retained as much of the timber structural elements, floors and windows as we could.” To assess the condition and strength of the timber, the contractor carried out tests using a resistograph. “We strengthened the timber structure with bonded steel plates, anchored using threaded rods. We repaired beams with
minor damage using epoxy prostheses,” says Filip Van Straeten, project director at PIT-EIFFAGE.
During the design phase, the structural engineer assessed the load-bearing capacity of all the floors, and measures were taken where necessary to increase it. “Where it was not possible to retain the old windows, we made new ones based on the original designs. This was entirely bespoke work.” The glazing is new, with argon gas between the panes. “The outer pane is drawn glass, so that the glazing also has the appearance of the historic windows.”

New building services
“The building services are entirely new. To comply with the regulations, which require only necessary measures that do not, or only minimally, affect heritage value, we assessed for each house where internal insulation could be installed. For buildings with rendered façades, we also considered insulating façade render. For insulation, which was virtually non-existent in the past but is now mandatory, we installed hemp-lime linings. This is a new application of an old technique. We insulated the roofs with a modern material, namely glass wool. We finished some of the floors with timber and others with Boomse tiles. Here too, we installed high-performance modern insulation (PIR),” says Raf Vandeweyer. “Concealing the HVAC, water and electrical services was a major challenge. We made use of the existing chimney flues wherever possible.”
“This project had a very long lead time,” the architect notes. “During the works, Flemish legislation changed. We therefore had to reassess which interventions we could make to reduce energy demand, and what impact those measures would have on heritage value and the experience of the buildings. For example, it turned out that heat pumps could only be used to a limited extent, while installing PV panels was ruled out.”
PROJECT DETAILS
Client OCMW Lier
Architect Architecten Beeck & Hermans (Mechelen)
Main contractor(s) PIT-EIFFAGE (Kapellen)
Question about this story? Ask your question
Who worked on it
Liers Begijnhof in Lier, restauratie
- contractor
Denys - clientOCMW Lier
- architectArchitecten Beeck & Hermans
- main contractorPIT-EIFFAGE
Keep following this
Get an email when a new story is published. No account needed.
- ProjectLiers Begijnhof
- SubjectMonuments
- CompanyOCMW Lier
- CompanyArchitecten Beeck & Hermans
- CompanyPIT-EIFFAGE


















