Acoustics in historic buildings: a delicate balancing act
Text Tim JanssensImage Toon Grobet, Tim Janssens

Acoustics in restoration and adaptive reuse projects is a discipline in its own right. How can you ensure that acoustic interventions do not compromise the historic and aesthetic value of an existing building or listed monument? This was one of the many questions discussed during the interactive webinar that architectura and Palindroom recently organised on this highly topical subject. On one point, the panellists and the many viewers were in complete agreement: “The fact that a project involves restoration or adaptive reuse does not mean that you should automatically lower your standards.”
The setting for the webinar on acoustics could hardly have been more appropriate for this article. It was broadcast from Kapel De Waterhond in Sint-Truiden, a sixteenth-century monument that Klaarchitectuur has converted into its offices. The result is a stunning adaptive reuse project that has attracted considerable national and international attention for the architecture practice. “From the outset, we decided to keep the chapel as intact as possible and use its bare shell as a backdrop for four staggered box-in-box volumes containing the offices, reception and meeting room, sanitary facilities and so on,” says architect and managing director Gregory Nijs. “The acoustics are excellent not only in those box-in-box volumes, but also in the adjoining multipurpose space, without requiring too many interventions or aesthetic compromises.”

Do not lower standards from the outset
In this respect, Kapel De Waterhond is the exception that proves the rule. In general, getting the acoustics right in historic buildings while also meeting all the other constraints, such as preserving heritage value, is often no easy task. One important question raised during the webinar was therefore whether acoustic standards can be lowered from the outset in restoration and adaptive reuse projects. Arnout Stevens, Lead Contract Engineer Noise at Vinçotte, says they cannot, as did the majority of the other construction professionals who attended the webinar: “If you lower the standards from the outset, the result will inevitably be worse.” Marjolein Vandersickel, acoustic expert at VK architects+engineers, part of Sweco, also disagrees with this view. “I think you should set the bar as high as you would for a new-build project. However, other constraints, such as fire safety and structural stability, will arise during the design and construction process, so you will have to make choices. In other words, you have to find a balance between the many other requirements, but dismissing acoustics from the outset simply because it is a restoration or adaptive reuse project is not a good idea.”
An exceptionally difficult puzzle at Wintercircus
The Wintercircus in Ghent, a prestigious project known to many, demonstrates how challenging it can be to reconcile acoustics with other constraints in a restoration or adaptive reuse project. One of the standout features in this respect is the underground rock venue beneath the circular central arena. “It was designed as a concrete box-in-box structure, using the mass-spring-mass principle to prevent sound from escaping the space. By separating the sound-absorbing and sound-insulating layers, we arrived at walls around 75 cm thick. We did not clad the supporting columns with a lining wall, but the structure above is mounted on the columns with vibration isolation,” explains Marjolein Vandersickel. The biggest challenge, however, was renovating the roof, which had to be upgraded in terms of structural stability, fire safety and acoustics, without adding any extra weight to it. “We created a completely independent structure, taking into account, among other things, the presence of the smoke and heat exhaust system. It took a lot of work to find the ideal build-up, down to the kilogram per square metre. We are very proud to have solved this exceptionally difficult puzzle.”

Making appropriate use of the existing building
A specific case cited by Arnout Stevens shows that it is unfortunately not always possible to improve the acoustics of historic buildings: the extension and restoration of the Beurs van Brussel, overseen by Robbrecht en Daem architecten, with an acoustic design by Kahle Acoustics. “In the grand, open entrance hall of the imposing exchange building, the greatest challenge was room acoustics, you might say acoustics squared. Speech intelligibility was a key consideration in checking the voice alarm system for fire evacuation. Given the high ceilings and large spaces, as well as the original sound-reflective finishes in natural stone and glass, reverberation times are long. This can, among other things, encourage the Lombard effect, that is, people’s tendency to speak more loudly in noisy environments, resulting in acoustic soup. Unfortunately, speech intelligibility could not be improved enough to meet the standards without substantially affecting the building’s valuable architecture. You have to work within the constraints you are given, and sometimes they are incompatible with good acoustics, although a lot also depends on the intended function. I believe in any case that adaptive reuse projects should be better aligned with a building’s original use, and that contemporary additions do not always add value. Solid church walls 60 cm thick, for example, can be worth their weight in gold acoustically, so it would be a shame to cut openings in them or otherwise treat them irresponsibly. The same applies to spaces with timber floors, which obviously should not be turned into dance halls. In other words, the success of an adaptive reuse project depends greatly on the architect’s mindset.”
Question about this story? Ask your question
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectAcoustics
- CompanyVK architects+engineers