BIM facilitates data validation and circularity in prestigious pilot project

The new headquarters of Buildwise, formerly WTCB, proves that energy renovation need not be inferior to new-build construction. The striking office building is conceived as a living laboratory promoting digital and circular construction. The fact that this prestigious project, designed by BOVAArchitects, can rightly be called a textbook example of innovation and future-proofing is due in large part to the extensive use of BIM. Anthony Kennes, BIM manager at engineering consultancy Sweco, explains how this advanced collaborative methodology paid off from start to finish.

When an innovation and expertise centre embarks on a building project of its own, it goes without saying that nothing is left to chance in terms of architectural and technical ingenuity. The bar was therefore set very high for the new Buildwise building, created through the circular renovation of a postmodern office complex in Kleine Kloosterstraat in Sint-Stevens-Woluwe. For BOVAArchitects, the existing concrete structure provided the starting point for creating a high-tech base with 6,500 m² of usable above-ground floor area. Its eye-catching features include the unusual atrium, which will be used, among other things, for research and experiments with drones, and the impressive green façade, which the architects conceived, based on a unique concept, as a vertical test garden for urban greening.
Digital catalyst
Buildwise saw the construction of its new headquarters as an ideal showcase for promoting digital and circular construction. That is why BIM was a major focus under the leadership of Bureau Bouwtechniek. “At Sweco, too, we try to be pioneers in BIM,” says Anthony Kennes, an architect by training who has been working in BIM for eight years. “In our view, BIM is first and foremost a digital catalyst for better collaboration between all the construction professionals involved, both internally and externally. The Common Data Environment (CDE) is therefore at least as important to the efficient delivery of a project as the BIM model itself. This was once again borne out in this project, which was intended to be a model of digital collaboration. Relations and communication between client Buildwise, architect BOVAArchitects, Bureau Bouwtechniek (which developed the BIM model and coordinated and developed it across disciplines), engineering consultancy Boydens Engineering part of Sweco, structural engineering firm Ney & Partners and contractor Vanhout were excellent. Using a Common Data Environment made the models, drawings and other data accessible to everyone, even without any knowledge of complex 3D software. This allows everyone to consult the necessary information and provide feedback. It helped us make the right decisions, gain greater insight, systematically monitor issues and avoid clashes between the different construction disciplines.”

Data collection and validation
One of the main aims of this prestigious pilot project was to use BIM to carry out a data-driven energy and circular renovation, thereby creating additional value. “In other words, this project gave us plenty of scope to put our skills to use, not only in our engineering work, but also in collecting and validating data via the BIM model,” explains Anthony Kennes. “Using dynamic simulations, we worked with building physics consultancy Daidalos Peutz to optimise various aspects during the design phase, including the insulation envelope, type of glazing, cooling and heating system, and energy performance. That data can also be put to excellent use during the operational phase. An audit is carried out every three months to check whether the calculated results are accurate and what energy savings can be achieved at that point. In the future, we will also be able to use Model Predictive Control, in other words, to make intelligent predictions based on certain parameters (weather conditions, occupancy levels, etc.) using model data, and control the building more energy-efficiently. In projects where we already apply this approach, we have achieved energy savings of up to 40%.”

Modular and circular
BIM also proved invaluable to the circularity of the new Buildwise building. BOVAArchitects conceived the structure as a modular materials database, with a strong focus on prefabrication and demountability. “In innovative projects like this, it is important to map everything out properly in advance. This was done using 3D scanning and BIM. Following the demolition phase, a great many materials were already reused based on an inventory of the existing building. Buildwise also now has a comprehensive overview of all the additional new materials, which is extremely useful in view of a future renovation or conversion. Since everything has been worked out down to the smallest detail in the BIM model, it is immediately clear how and in what order certain building elements were assembled. Finally, the new Buildwise building includes an experience centre for construction professionals, with a dedicated VR space where the BIM model can be brought to life. All this makes the added value of BIM in this project particularly significant.”
Een zakelijke vraag aan Sweco Belgium? Get in touch
Who worked on it
Hoofdzetel Buildwise in Zaventem, renovatie
- engineering consultancy
Sweco - clientBuildwise
- architectBOVAArchitects
- interdisciplinair coördineerdeBureau Bouwtechniek
- engineering consultancyBoydens Engineering
- stabiliteitsbureauNey & Partners
- contractorVanhout
- bouwfysisch ingenieursbureauDaidalos Peutz
Keep following this
Get an email when a new story is published. No account needed.
- ProjectHoofdzetel Buildwise
- SubjectBIM
- CompanySweco Belgium
- CompanyBuildwise
- CompanyBOVAArchitects
- CompanyBureau Bouwtechniek
- CompanyBoydens Engineering