Sophisticated BIM tools make complex geometry possible
Text Mark de Lau, Tim JanssensImage Construsoft

BIM offers designers limitless creative and construction possibilities. This was once again demonstrated by the construction of the Govan-Partick Bridge in Glasgow, the largest opening bridge in Europe, which is due to open in spring 2024. A project that presented a range of challenges, but was successfully delivered thanks to a combination of software applications including Tekla Structures, Rhino, Grasshopper and Trimble Connect.
It is common knowledge that Victor Buyck Steel Construction, a leading international steel construction company, enjoys taking on complex and unusual projects. The company reinforced this reputation with the construction of the Govan-Partick Bridge, a new cycle and pedestrian bridge with a total length of 110 metres, which recently began spanning the River Clyde. Bruno De Roo, Project Draughtsman at Victor Buyck: “The first bridge I drew up for Victor Buyck was a huge challenge, because everything was in 2D. When I was given the opportunity to take a course in Tekla Structures, I was really enthusiastic. It is a very powerful package.” He now models bridges such as the Govan-Partick Bridge in BIM with his colleague Dana Verstringe. Bruno De Roo: “The Govan-Partick Bridge consists of two long steel main box girders with a deck plate between them, supported by longitudinal and transverse stiffeners. The deck is supported entirely by the stays connected to the pylons, whose design is based on the historic cranes along the river. The whole structure rests on a kind of slewing ring.”

Various challenges
This distinctive infrastructure project presented a range of challenges. Bruno De Roo: “There were several difficulties. First, there was the geometry, with curved and rotated plates. Also, from the outside you cannot see how many internal stiffeners are needed, so every plate had to be welded on both sides. We had to analyse each section of the bridge separately to work out how to build it. A third challenge was the weight of the bridge. The centre of gravity is extremely important, as the bridge rotates on a slewing ring that is not positioned centrally along the length of the bridge. We first worked out the centre-of-gravity checks theoretically in the model, then verified in practice that the results matched. This would not have been possible without the right software.”

Combining software applications
Alongside Tekla Structures, his colleague Dana Verstringe also used Grasshopper and Rhino for this project: “We use Grasshopper to programme the geometry visually. Rhino is used to convert it into a visual model. This allows us to transfer the skeleton, or model structure, in layers via the reference models in Tekla Structures. If anything changes in the geometry, we can easily update it. We also often use the Tekla Live Link feature in Grasshopper’s plug-in environment. This makes it possible to control plates from Grasshopper in Tekla Structures in real time. By combining various software applications, we were able to tackle all the challenges quickly and efficiently.”
No surprises thanks to augmented reality
Since last year, Victor Buyck has also been using augmented reality (AR) in production planning and manufacturing. “Our models are often busy, as they are full of lines. It is not always easy to turn them into a 3D model, decide how components should be welded or determine the construction sequence. We use Trimble Connect for this,” explains Bruno De Roo. “In Trimble Connect, you can see which plate part number needs to be welded in where, and a video showing the construction sequence is generated, with a step-by-step plan or assembly sequence using the views created. In the near future, we plan to innovate further with the Trimble Connect AR app, allowing us to view a project’s components on site at an early stage. This ensures we are not caught by surprise.”

Good communication with partners through BIM
BIM remains an extremely important tool for Victor Buyck. So it is no surprise that the company won a Construsoft BIM Award for the Govan-Partick Bridge in the ‘Infrastructure projects’ category. Bruno De Roo: “BIM allows us to exchange information with subcontractors. More importantly, I think, we can share ideas for solving challenges in the model, in this case, for example, the slewing ring. I received the information for this from a subcontractor. BIM is now contractually stipulated on most projects. This gives the client ongoing insight into the project’s progress. It is also very useful to review the schedule during meetings with project partners.”
Watch the video about this project at www.construsoft.nl/brug-victor-buyck.
Have a business enquiry for Construsoft? Get in touch
Who worked on it
Govan-Partick Bridge in Glasgow
- Trimble Connect
Trimble
Keep following this
Get an email when a new story is published. No account needed.
- ProjectGovan-Partick Bridge
- SubjectBIM
- CompanyTrimble Inc
- CompanyConstrusoft